Implementation Strategy
Implementation of the Rio Reimagined Active Transportation Study will require sustained coordination among the jurisdictions, agencies, tribal communities, and community partners responsible for planning, funding, constructing, and maintaining active transportation facilities throughout the study area. Because bicycle and pedestrian trips frequently cross jurisdictional boundaries, implementation should focus on building a connected regional network rather than advancing individual projects in isolation. Continued multi-agency coordination will allow partners to strategically position priority active transportation projects for grant funding, leverage related investments, and respond efficiently as implementation opportunities become available.
Prioritization should also consider project readiness and the ability to leverage available funding. Projects with established concepts, preliminary cost estimates, identified right-of-way, community support, or completed preliminary engineering may be positioned to advance quickly when grant opportunities arise and have been identified.
The partnerships established through development of this Study should continue through implementation. Participating agencies should maintain an ongoing coordination framework focused specifically on advancing bicycle, pedestrian, shared-use path, trail connection, crossing, and access improvements identified through the Study. This can be done as a regular semi-annual meeting or using an interactive dashboard to update shared progress.
Each jurisdiction can continue to sponsor and deliver projects within its authority while coordinating with neighboring agencies on facilities that form part of the broader Rio Reimagined active transportation network. This coordination is particularly important at jurisdictional boundaries, where differences in project timing, facility design, or funding availability can create gaps in otherwise continuous routes.
Partners should periodically revisit the capital improvement planning section of this study, review priority projects, identify critical network gaps, coordinate upcoming improvements, and determine where joint action would accelerate implementation. This regional perspective can help ensure that investments made by individual agencies collectively create continuous and useful connections between neighborhoods, the river corridor, transit, schools, employment areas, parks, and other destinations.
Participating agencies should develop an ongoing, coordinated approach to pursuing active transportation funding. Rather than responding independently to individual grant opportunities, partners should regularly review upcoming federal, state, regional, and local funding programs and identify which projects are best positioned to compete.
Coordination can help agencies match projects to funding opportunities based on project readiness, eligibility, safety benefits, connectivity, community need, and the objectives of each funding program. It can also reduce unnecessary competition among partner agencies and identify opportunities for joint or complementary applications.
Grant applications should demonstrate how individual projects contribute to the larger Rio Reimagined active transportation network. Projects that close a network gap, eliminate a barrier, improve a difficult crossing, extend an existing bikeway or shared-use path, or connect multiple jurisdictions may be particularly well positioned when their regional significance is clearly documented.
Where appropriate, agencies should pursue coordinated applications for groups of related improvements. A series of bicycle and pedestrian projects that collectively creates a continuous route may present a stronger funding case than the same improvements pursued independently. Maintaining a “rising tide lifts all boats” mindset through implementation allows each agency to leverage their participation in the Rio Reimagined partnership to maximize regional impact and enhance competitiveness for funding opportunities.
A central implementation priority should be advancing recommended projects to a level of readiness that allows agencies to respond quickly when funding becomes available. Active transportation grant programs can be highly competitive and may provide relatively short application windows. Maintaining a pipeline of well-defined projects can significantly improve the ability of participating agencies to pursue these opportunities.
For priority projects, agencies should progressively complete the work needed to support future funding applications, including project scoping, conceptual design, preliminary cost estimates, community engagement, feasibility analysis, environmental review, right-of-way assessment, and preliminary engineering, and draw upon the data collected as part of this study for leverage, as appropriate.
The project pipeline should include improvements at different stages of readiness and varying levels of cost and complexity. This will allow partners to match available funding opportunities with appropriate projects rather than waiting for a funding program before beginning project development. Please utilize the interactive capital improvement planning table within this chapter for reference.
Partners should periodically update the status of priority projects, including project readiness, estimated cost, remaining development needs, potential funding sources, responsible agency, and anticipated implementation timeframe.
Funding and implementation decisions should emphasize projects that provide the greatest benefit to the overall active transportation network. In addition to considering individual project benefits, agencies should evaluate how each improvement contributes to network continuity and connectivity.
Priority should be given to opportunities that close gaps between existing facilities, address barriers to walking and bicycling, improve crossings of major roadways or other physical barriers, connect existing bikeways and shared-use paths, and improve access between communities and key destinations.
This network-based approach can also strengthen grant applications by demonstrating that proposed projects build upon previous public investments. Completing a relatively short missing connection, for example, may unlock the value of existing facilities on either side of the gap and create a substantially longer continuous route.
Active transportation projects should be packaged to align with the scale and objectives of available funding programs. In some cases, a single intersection, crossing, trail connection, or bikeway segment may be appropriate for an individual funding request. In other cases, several related improvements may be combined into a corridor or network project that demonstrates greater connectivity and regional benefit.
Larger projects should also be structured so they can be implemented in logical phases when full funding is not immediately available. Each phase should provide a functional active transportation benefit while contributing toward completion of the larger network.
Partners should identify opportunities to coordinate project limits across jurisdictional boundaries so that grant applications can demonstrate continuous improvements rather than stopping at agency boundaries. Where a joint application is not practical, agencies can pursue complementary projects and coordinate schedules, design standards, and project termini.
One of the most effective implementation strategies will be to incorporate recommended active transportation improvements into planned roadway, bridge, transit access, trail, flood control, and other short-term infrastructure projects. Agencies should routinely compare their capital improvement programs and planned transportation projects against the Study’s recommended active transportation network.
When a roadway is reconstructed, resurfaced, or otherwise substantially improved, agencies should evaluate opportunities to incorporate recommended bicycle and pedestrian facilities as part of the project. Similarly, bridge, intersection, drainage, and transit access projects should be reviewed for opportunities to improve crossings and connections for people walking and bicycling.
As individual projects move into design, participating agencies should coordinate facility types, project termini, wayfinding, and other design elements where routes cross jurisdictional boundaries. The objective should be to create an active transportation network that functions as a continuous system from the user’s perspective, even when individual segments are owned or maintained by different agencies.
Coordination should begin early enough to resolve differences in project schedules, design approaches, and connection points. Particular attention should be given to locations where existing or planned facilities change jurisdiction, intersect with major roadways, connect with shared-use paths, or transition between different facility types.
The Rio Reimagined active transportation implementation program should be treated as an ongoing effort. Participating agencies should periodically review the status of priority projects, identify upcoming active transportation grant opportunities, and determine which projects should be advanced for the next funding cycle.
This process should also track completed projects and remaining network gaps so that priorities can evolve as the system is built. As individual improvements are implemented, the focus can shift toward the next connections necessary to create continuous routes.
Through sustained multi-agency coordination, a pipeline of grant-ready projects, strategic funding pursuits, and an emphasis on network completion, Rio Reimagined partners can incrementally implement the Study’s recommendations and create a connected active transportation network that extends across jurisdictional boundaries and ultimately maximizes active transportation access and opportunity for the region.
Trail Alignment Recommendations
Prioritizing Investment
Implementation of the Rio Reimagined active transportation network will occur incrementally as funding, partnerships, and project opportunities become available. Because available resources are unlikely to support all recommended improvements at once, participating agencies should strategically prioritize investments that provide meaningful near-term benefits while advancing the long-term vision for a continuous regional trail and multi-use path network.
Particular emphasis should be placed on projects that close critical gaps, connect existing trail and multi-use path segments, overcome physical barriers, improve safe crossings, and extend access to destinations and communities that are currently disconnected from the network. Relatively short improvements that connect existing facilities may provide substantial value by creating longer, continuous routes and maximizing the benefit of previous investments.
Project Readiness and Funding Availability
Prioritization should also consider project readiness and the ability to leverage available funding. Projects with established concepts, preliminary cost estimates, identified right-of-way, community support, or completed preliminary engineering may be positioned to advance quickly when grant opportunities arise and have been identified in the Capital Improvement section of this study. At the same time, agencies should continue investing in planning and design for longer-term priority projects so that a lack of project readiness does not become a barrier to obtaining future funding.
Leverage Related Projects
A project's ability to leverage other planned investments should also inform implementation decisions. Opportunities may arise to incorporate trail and multi-use path improvements into roadway reconstruction, bridge projects, drainage improvements, transit access projects, or other programmed capital investments. Coordinating active transportation improvements with projects that are already funded or under development can reduce costs, avoid future reconstruction, and accelerate delivery.
Consider Regional Benefit
Projects that demonstrate multi-agency or regional benefits should receive particular consideration for coordinated investment. Improvements that cross jurisdictional boundaries, connect facilities owned by different agencies, or complete routes serving multiple communities can provide benefits beyond those achievable through isolated investments. Partner agencies should coordinate project timing and funding pursuits so that improvements on one side of a jurisdictional boundary are supported by complementary investments on the other.
Diversification of Project Types
Investment should also balance near-term implementation opportunities with development of major long-term connections. Lower-cost projects, gap closures, crossing improvements, and other readily implementable improvements can demonstrate progress and provide immediate benefits. Concurrently, agencies should advance feasibility studies, environmental review, preliminary engineering, and right-of-way activities for larger or more complex trail projects that will require multiple funding cycles to deliver. As conditions and funding programs change, investment priorities should be revisited periodically rather than treated as a fixed project ranking. A project that is not immediately ready for implementation may become a near-term opportunity because of a new grant program, adjacent capital project, development activity, or partnership. Maintaining an adaptable portfolio of projects at different stages of readiness will allow Rio Reimagined partners to respond strategically to these opportunities.
Prioritization Criteria
When determining where to direct limited implementation resources, agencies should generally consider:
-
Network Connectivity
Does the investment close a gap or create a continuous trail or multi-use path connection?
-
Safety
Does it address a significant barrier, crossing, or condition that limits safe walking and bicycling?
-
Access
Does it improve connections between communities and important destinations or expand access to the regional active transportation network?
-
Regional Benefit
Does it connect jurisdictions or complement investments being made by other agencies?
-
Project Readiness
Can the project reasonably advance within the timeframe of available funding?
-
Funding Competitiveness
Does the project align with the objectives and eligibility requirements of available grant programs?
-
Leveraging Opportunities
Can the project be coordinated with another planned or funded capital improvement?
-
Implementation Feasibility
Are right-of-way, environmental, design, maintenance, and other delivery considerations reasonably understood?
-
Community Support
Does the project respond to needs and priorities identified through community and stakeholder engagement?
Using these considerations, participating agencies can direct limited resources toward projects that both deliver immediate active transportation benefits and contribute to completion of the larger Rio Reimagined network. The objective should not be to establish a static sequence of projects, but to maintain a strategic investment pipeline that enables agencies to advance the right project when funding, partnerships, and implementation opportunities align. Reference the table in the Capital Improvement Planning section of this Study for more information on prioritized projects and short-, mid-, and long-term investments by agency.
Capital Improvement Plan
The Rio Reimagined Active Transportation Plan represents the next chapter in more than 60 years of planning, visioning, environmental stewardship, recreation development, floodplain management, and economic revitalization efforts along the Salt, Gila, Agua Fria, and Hassayampa river systems.
Corridor Segment Prioritization
| Segment Name | Segment Location | Area | Jurisdiction | Agency | Pathway Section | Location | Width | Material | Miles | Acquisition / Easement Required | Relative Order of Magnitude | Priority |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Old Highway 80 (Arlington) | Gillespie Dam Bridge to Salome Highway | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 11.04 | No | $13,794,744 | Mid-Term |
| Old Highway 80 - Segment A | Gillespie Dam Bridge to Desert Rose Rd | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 4 | No | $4,995,265 | Mid-Term |
| Old Highway 80 - Segment B | Desert Rose Rd tp Cactus Rose Rd | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.99 | No | $2,485,795 | Mid-Term |
| Old Highway 80 - Segment C | Cactus Rose Road to Arlington School Rd | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 0.97 | No | $1,207,386 | Mid-Term |
| Old Highway 80 - Segment D | Arlington Arlington School Rd to 319th Ave | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 3.13 | No | $3,906,250 | Mid-Term |
| Old Highway 80 - Segment E | 319th Avenue to Salome Highway | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 0.96 | No | $1,200,047 | Mid-Term |
| Arlington Canal Road (Arlington) | Old Highway 80 to W. Dobbins Butte Game Rd | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.86 | Yes | $3,574,337 | Long-Term |
| Arlington Canal Road - Segment A | Old Highway 80 to 319th Ave | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.09 | No | $2,614,110 | Long-Term |
| Arlington Canal Road - Segment B | 319th Ave to Future South Bank Alignment | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 0.77 | Yes | $960,227 | Long-Term |
| 319TH Avenue (Arlington) | 319th Ave to Old Highway 80 | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.72 | No | $2,150,568 | Long-Term |
| 319TH Avenue | 319th Ave to Old Highway 80 | Arlington | Maricopa County | MCDOT | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.72 | No | $2,150,568 | Long-Term |
| Ultimate North Bank (Buckeye / Goodyear) | 319th Ave to Johnson Rd to Citrus Ln | Buckeye | City of Buckeye | Buckeye | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 20.51 | Yes | $25,640,388 | Long-Term |
| Ultimate North Bank (Buckeye) - Segment A | 319th Ave to Johnson Rd | Buckeye | City of Buckeye | Buckeye | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.32 | Yes | $2,893,939 | Long-Term |
| Ultimate North Bank (Buckeye) - Segment B | North Bank - Johnson Rd to Palo Verde Rd | Buckeye | City of Buckeye | Buckeye | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.05 | Yes | $2,563,684 | Long-Term |
| Ultimate North Bank (Buckeye) - Segment C | North Bank - Palo Verde Rd to Turner Rd | Buckeye | City of Buckeye | Buckeye | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.34 | Yes | $2,923,059 | Long-Term |
| Ultimate North Bank (Buckeye) - Segment D | North Bank - Turner Rd to Rooks Rd | Buckeye | City of Buckeye | Buckeye | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.17 | Yes | $2,707,623 | Long-Term |
| Ultimate North Bank (Buckeye) - Segment E | North Bank - Rooks Rd to Apache Rd | Buckeye | City of Buckeye | Buckeye | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.23 | Yes | $2,784,801 | Long-Term |
| Ultimate North Bank (Buckeye) - Segment F | North Bank - Apache Rd to Rainbow Rd | Buckeye | City of Buckeye | Buckeye | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.39 | Yes | $2,982,955 | Long-Term |
| Ultimate North Bank (Buckeye) - Segment G | North Bank - Rainbow Rd to Verrado Way | Buckeye | City of Buckeye | Buckeye | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.1 | Yes | $2,627,841 | Long-Term |
| Ultimate North Bank (Buckeye) - Segment H | North Bank - Verrado Way to Perryville Rd | Buckeye | City of Buckeye | Buckeye | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.93 | Yes | $3,661,695 | Long-Term |
| Ultimate North Bank (Buckeye) - Segment I | North Bank - Perryville Rd to Citrus Ln | Goodyear | City of Goodyear | Goodyear | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2 | Yes | $2,494,792 | Long-Term |
| North Bank Connector (Goodyear) | Goodyear North Bank Connector - Estrella Parkway to Bullard Avenue | Goodyear | City of Goodyear | Goodyear | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 0.96 | Yes | $1,201,468 | Long-Term |
| North Bank Connector (Goodyear) | Goodyear North Bank Connector - Estrella Parkway to Bullard Avenue | Goodyear | City of Goodyear | Goodyear | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 0.96 | Yes | $1,201,468 | Long-Term |
| Buckeye Canal (BUCKEYE) | Buckeye Canal - Old Hwy 80 to Perryville Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 18.12 | Yes | $22,649,858 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment A | Buckeye Canal - Buckeye canal Rd to Johnson Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 2.27 | Yes | $2,840,909 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment B | Buckeye Canal - Johnson Rd to Bruner Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.48 | Yes | $1,846,591 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment C | Buckeye Canal - Bruner Rd to Palo Verde Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.33 | Yes | $1,657,197 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment D | Buckeye Canal - Palo Verde Rd to Wilson Ave | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.04 | Yes | $1,302,083 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment E | Buckeye Canal - Wilson Ave to Turner Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.02 | Yes | $1,278,409 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment F | Buckeye Canal - Turner Rd to MC 85 | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1 | Yes | $1,254,735 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment G | Buckeye Canal - MC 85 to Rooks Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.04 | Yes | $1,302,083 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment H | Buckeye Canal - Rooks Rd to Miller Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.02 | Yes | $1,278,409 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment I | Buckeye Canal - Miller Rd to Apache Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.06 | Yes | $1,325,758 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment J | Buckeye Canal - Apache Rd to Watson Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1 | Yes | $1,254,735 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment K | Buckeye Canal - Watson Rd to Rainbow Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.08 | Yes | $1,349,432 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment L | Buckeye Canal -Rainbow Rd to Dean Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.02 | Yes | $1,278,409 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment M | Buckeye Canal - Dean Rd to Verrado Way | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.04 | Yes | $1,302,083 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment N | Buckeye Canal - Verrado Way to Jackrabbit Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.61 | Yes | $2,012,311 | Mid-Term |
| Buckeye Canal (BUCKEYE) - Segment O | Buckeye Canal - Jackrabbit Rd to Perryville Rd | Buckeye | City of Buckeye | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.09 | Yes | $1,366,714 | Mid-Term |
| Buckeye Canal (Goodyear) - Section 1 | Buckeye Canal - Perryville Rd to Estrella Parkway | Goodyear | City of Goodyear | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 4.24 | Yes | $5,299,479 | Mid-Term |
| Buckeye Canal (Goodyear) - Segment P | Buckeye Canal - Perryville Rd to Citrus Rd | Goodyear | City of Goodyear | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 0.99 | Yes | $1,237,453 | Mid-Term |
| Buckeye Canal (Goodyear) - Segment Q | Buckeye Canal - Citrus Rd to Cotton Ln | Goodyear | City of Goodyear | BWDCD | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.08 | Yes | $1,349,432 | Mid-Term |
| Buckeye Canal (Goodyear) - Segment R | Buckeye Canal - Cotton Ln to Sarival Ave | Goodyear | City of Goodyear | BWDCD | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.08 | Yes | $1,349,432 | Mid-Term |
| Buckeye Canal (Goodyear) - Segment S | Buckeye Canal - Sarival Ave to Estrella Parkway | Goodyear | City of Goodyear | BWDCD | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.09 | Yes | $1,363,163 | Mid-Term |
| Buckeye Canal (Goodyear) - Section 2 | Buckeye Canal - Estrella Parkway to Litchfield Rd | Goodyear | City of Goodyear | BWDCD | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.57 | Yes | $3,217,330 | Mid-Term |
| Buckeye Canal (Goodyear) - Segment T | Buckeye Canal - Estrella Parkway to Bullard Ave | Goodyear | City of Goodyear | BWDCD | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.08 | Yes | $1,349,432 | Mid-Term |
| Buckeye Canal (Goodyear) - Segment U | Buckeye Canal - Bullard Ave to Litchfield Rd | Goodyear | City of Goodyear | BWDCD | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.49 | Yes | $1,867,898 | Mid-Term |
| Buckeye Canal (Avondale) | Buckeye Canal - Litchfield Rd to El Mirage Rd | Avondale | City of Avondale | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 2.24 | Yes | $2,795,928 | Mid-Term |
| Buckeye Canal (Avondale ) - Segment V | Buckeye Canal - Litchfield Rd to Vermeersch Rd | Avondale | City of Avondale | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.18 | Yes | $1,470,170 | Mid-Term |
| Buckeye Canal (Avondale ) - Segment W | Buckeye Canal - Vermeersch Rd to El Mirage Rd | Avondale | City of Avondale | BWDCD | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.06 | Yes | $1,325,758 | Mid-Term |
| North Bank (Avondale) | North Bank - Agua Fria River to El Mirage Rd | Avondale | City of Avondale | Avondale | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.93 | Yes | $2,412,169 | Long-Term |
| North Bank (Avondale) | North Bank - Agua Fria River to El Mirage Rd | Avondale | City of Avondale | Avondale | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 1.93 | Yes | $2,412,169 | Mid-Term |
| El Mirage Road (Avondale) | El Mirage Rd - Buckeye Canal to Gila River North Bank | Avondale | City of Avondale | BWDCD / Avondale | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 0.74 | No | $923,295 | Long-Term |
| El Mirage Road - Buckeye Canal to Gila River North Bank | El Mirage Rd - Buckeye Canal to Gila River North Bank | Avondale | City of Avondale | BWDCD / Avondale | Levee Pathway | Alternate North Bank | 16 FT Wide | Asphalt / Concrete | 0.74 | No | $923,295 | Long-Term |
| North Bank (Avondale) | North Bank - El Mirage Rd to 107th Ave | Avondale | City of Avondale | Avondale | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.05 | Yes | $2,557,528 | Long-Term |
| North Bank - El Mirage Rd to 107th Ave (Avondale) - Segment A | North Bank - El Mirage Rd to 107th Ave | Avondale | City of Avondale | Avondale | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 2.05 | Yes | $2,557,528 | Long-Term |
| North Bank (Phoenix) - Section 1 | North Bank - 107th Ave to 7th Ave (Phoenix) | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 13.73 | Yes | $17,159,564 | Long-Term |
| North Bank (Phoenix) - Segment B | North Bank - 107th Ave to 99th Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.04 | No | $1,301,373 | Long-Term |
| North Bank (Phoenix) - Segment C | North Bank - 99th Ave to 91st Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.16 | No | $1,444,129 | Long-Term |
| North Bank (Phoenix) - Segment D | North Bank - 91st Ave to 83rd Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.31 | $1,633,523 | Long-Term | |
| North Bank (Phoenix) - Segment E | North Bank - 83rd Ave to 75th Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.12 | Yes | $1,396,780 | Long-Term |
| North Bank (Phoenix) - Segment F | North Bank - 75th Ave to 67th Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.14 | $1,420,455 | Long-Term | |
| North Bank (Phoenix) - Segment G | North Bank - 67th Ave to 59th Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.23 | Yes | $1,538,826 | Long-Term |
| North Bank (Phoenix) - Segment H | North Bank - 59th Ave to 51st Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.04 | No | $1,302,083 | Long-Term |
| North Bank (Phoenix) - Segment I | North Bank - 51st Ave to 43rd Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.36 | $1,704,545 | Long-Term | |
| North Bank (Phoenix) - Segment J | North Bank - 43rd Ave to 35th Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.02 | $1,278,409 | Long-Term | |
| North Bank (Phoenix) - Segment K | North Bank - 35th Aven to 27th Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.1 | $1,373,106 | Long-Term | |
| North Bank (Phoenix) - Segment L | North Bank - 27th Ave to 19th Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1 | $1,254,735 | Mid-Term | |
| North Bank (Phoenix) - Segment M | North Bank - 19th Ave to 7th Ave | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.21 | $1,511,600 | Short-Term | |
| North Bank (Phoenix) - Section 2 | North Bank (Phoenix) - 16th Street | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway | North Bank | 12 FT Wide | Concrete | 0.16 | $206,203 | Short-Term | |
| North Bank (Phoenix) - 16th Street | North Bank (Phoenix) - 16th Street | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway | North Bank | 12 FT Wide | Concrete | 0.16 | No | $206,203 | Short-Term |
| North Bank (Phoenix) - Section 3 | North Bank (Phoenix) - 24th Street | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway | North Bank | 12 FT Wide | Concrete | 0.57 | $713,068 | Short-Term | |
| North Bank (Phoenix) - 24th Street | North Bank (Phoenix) - 24th Street | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway | North Bank | 12 FT Wide | Concrete | 0.57 | $713,068 | Short-Term | |
| North Bank (Phoenix) - Section 4 | North Bank (Phoenix) - 24th St to 48th St | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 3.17 | $3,957,623 | Short-Term | |
| North Bank (Phoenix) - Segment N | North Bank (Phoenix) - 24th St to 32nd St | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 0.93 | $1,160,038 | Short-Term | |
| North Bank (Phoenix) - Segment O | North Bank (Phoenix) - 32nd St to 40th St | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.06 | $1,325,758 | Short-Term | |
| North Bank (Phoenix) - Segment P | North Bank (Phoenix) - 40th St to 48th St | Phoenix | City of Phoenix | Phoenix | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.16 | $1,448,153 | Short-Term | |
| North Bank (Tempe) - Section 5 | North Bank (Tempe) - 48th St to Priest Dr | Tempe | City of Tempe | Tempe | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.18 | $1,475,616 | Short-Term | |
| North Bank (Tempe) - Segment Q | North Bank (Tempe) - 48th St to Priest Dr | Tempe | City of Tempe | Tempe | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 1.18 | No | $1,475,616 | Short-Term |
| North Bank (Tempe) - Section 6 | North Bank (Tempe) - Miller Rd to McClintock Dr | Tempe | City of Tempe | Tempe | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 0.61 | Yes | $760,653 | Long-Term |
| North Bank (Tempe) - Segment R | North Bank (Tempe) - Miller Rd to McClintock Dr | Tempe | City of Tempe | Tempe | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 0.61 | Yes | $760,653 | Long-Term |
| North Bank (SRPMIC) - Section 7 | North Bank (SRPMIC) - McClintock Dr to Alma School Rd | SRPMIC | SRPMIC | SRPMIC | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 3.64 | Yes | $4,547,822 | Long-Term |
| North Bank (SRPMIC) - Segment 7 | North Bank (Mesa) - McClintock Dr to Alma School Rd | SRPMIC | SRPMIC | SRPMIC | Levee Pathway | North Bank | 16 FT Wide | Asphalt / Concrete | 3.64 | Yes | $4,547,822 | Long-Term |
| South Bank (Arlington) - Section 1 | South Bank (Arlington) - Gillespie Dam to 319th Ave | Arlington | Maricopa County | MCDOT | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 6.84 | Yes | $8,552,557 | Long-Term |
| South Bank (Arlington) - Segment A | South Bank (Arlington) - Gillespie Dam to Desert Rose Rd | Arlington | Maricopa County | MCDOT | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 3.64 | $4,545,928 | Long-Term | |
| South Bank (Arlington) - Segment B | South Bank (Arlington) - Desert Rose Rd to 319 Ave | Arlington | Maricopa County | MCDOT | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 3.21 | $4,007,102 | Long-Term | |
| South Bank (Buckeye) - Section 2 | South Bank (Buckeye) - 319th Ave to Perryville Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 18.81 | $23,511,127 | Long-Term | |
| South Bank (Buckeye) - Segment C | South Bank (Buckeye) - 319th Ave to Johnson Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.08 | $2,597,538 | Long-Term | |
| South Bank (Buckeye) - Segment D | South Bank (Buckeye) - Johnson Rd to Palo Verde Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.31 | $2,888,258 | Long-Term | |
| South Bank (Buckeye) - Segment E | South Bank (Buckeye) - Palo Verde Rd to Turner Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.23 | $2,793,561 | Long-Term | |
| South Bank (Buckeye) - Segment F | South Bank (Buckeye) - Turner Rd to Rooks Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.22 | $2,769,886 | Long-Term | |
| South Bank (Buckeye) - Segment G | South Bank (Buckeye) - Rooks Rd to Apache Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.27 | $2,840,909 | Long-Term | |
| South Bank (Buckeye) - Segment H | South Bank (Buckeye) - Apache Rd to Rainbow Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.35 | $2,935,606 | Long-Term | |
| South Bank (Buckeye) - Segment I | South Bank (Buckeye) - Rainbow Rd to Verrado Way | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.35 | $2,935,606 | Long-Term | |
| South Bank (Buckeye) - Segment J | South Bank (Buckeye) - Verrado Way to Perryville Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 3 | $3,749,053 | Long-Term | |
| South Bank (Goodyear) - Segment K | South Bank (Goodyear) - Perryville Rd to Citrus Ln | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.19 | $1,482,955 | Long-Term | |
| South Bank (Goodyear) - Segment L | South Bank (Goodyear) - Citrus Ln to Sarival Rd | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.5 | $3,125,000 | Long-Term | |
| South Bank (Goodyear) - Segment M | South Bank (Goodyear) - Sarival Rd to Bullard Ave | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.23 | $2,793,324 | Long-Term | |
| South Bank (Goodyear / Avondale) - Section 3 | South Bank (Goodyear) - Bullard Ave to Avondale Rd | Goodyear / Avondale | City of Goodyear / City of Avondale | Goodyear / Avondale | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 4.75 | Yes | $5,939,867 | Long-Term |
| South Bank (Goodyear) - Segment N | South Bank (Goodyear) - Bullard Ave to Litchfield Rd | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.18 | $1,480,824 | Long-Term | |
| South Bank (Avondale) - Segment O | South Bank (Avondale) - Litchfield Rd to El Mirage Rd | Avondale | City of Avondale | Avondale | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.49 | $3,111,979 | Long-Term | |
| South Bank (Avondale) - Segment P | South Bank (Avondale) - El Mirage Rd to Avondale Rd | Avondale | City of Avondale | Avondale | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.08 | $1,347,064 | Long-Term | |
| South Bank (Avondale / Phoenix) - Section 4 | South Bank (Avondale / Phoenix) - Avondale Rd to 15th Ave | Avondale / Phoenix | City of Avondale / City of Phoenix | Avondale / Phoenix | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 14.46 | Yes | $18,080,019 | Long-Term |
| South Bank (Avondale) - Segment Q | South Bank (Avondale) - Avondale Rd to 107th Ave | Avondale | City of Avondale | Avondale | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.01 | $1,263,731 | Long-Term | |
| South Bank (Phoenix) - Segment R | South Bank (Phoenix) 107th Ave to 99th Ave | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.14 | $1,421,402 | Long-Term | |
| South Bank (Phoenix) - Segment S | South Bank (Phoenix) 99th Ave to 83rd Ave | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.15 | $2,688,920 | Long-Term | |
| South Bank (Phoenix) - Segment T | South Bank (Phoenix) 83rd Ave to 67th Ave | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.22 | $2,777,462 | Long-Term | |
| South Bank (Phoenix) - Segment U | South Bank (Phoenix) 67th Ave to 51st Ave | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.68 | $3,354,167 | Long-Term | |
| South Bank (Phoenix) - Segment V | South Bank (Phoenix) 51st Ave to 35th Ave | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.2 | $2,746,212 | Long-Term | |
| South Bank (Phoenix) - Segment W | South Bank (Phoenix) 35th Ave to 15th Ave | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 3.06 | $3,828,125 | Long-Term | |
| South Bank - (Mesa) - South Canal - Section 5 | South Bank (Mesa) - South Canal - Alma School Rd to Center St | Mesa | City of Mesa | SRP | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.71 | Yes | $2,133,759 | Short-Term |
| South Bank (Mesa) - South Canal - Segment A | South Bank (Mesa) - South Canal - Alma School Rd to Center St | Mesa | City of Mesa | SRP | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.71 | Yes | $2,133,759 | Short-Term |
| South Bank - (Mesa) - South Canal - Section 6 | South Bank (Mesa) - South Canal - Mesa Dr to Power Rd | Mesa | City of Mesa | SRP | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 9.65 | Yes | $12,067,235 | Mid-Term |
| South Bank (Mesa) - South Canal - Segment B | South Bank (Mesa) - South Canal - Mesa Dr to Gilbert Rd | Mesa | City of Mesa | SRP | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.61 | Yes | $3,267,045 | Mid-Term |
| South Bank (Mesa) - South Canal - Segment C | South Bank (Mesa) - South Canal - Gilbert Rd to Val Vista Dr | Mesa | City of Mesa | SRP | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.14 | Yes | $2,675,189 | Mid-Term |
| South Bank (Mesa) - South Canal - Segment D | South Bank (Mesa) - South Canal - Val Vista Dr to Higley Rd | Mesa | City of Mesa | SRP | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.91 | Yes | $3,635,890 | Mid-Term |
| South Bank (Mesa) - South Canal - Segment E | South Bank (Mesa) - South Canal - Higley Rd to Power Rd | Mesa | City of Mesa | SRP | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 3.37 | Yes | $4,217,330 | Mid-Term |
| South Bank - (Mesa) - Tonto National Forest - Section 7 | South Bank (Mesa) - South Canal to Phon D Sutton Recreation Area | Mesa | City of Mesa | USDA | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 3.74 | Yes | $4,675,663 | Long-Term |
| South Bank (Mesa) - Tonto National Forest - Segment A | South Bank (Mesa) - South Canal to Granite Reef Recreation Area | Mesa | City of Mesa | SRP | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 0.79 | Yes | $992,188 | Long-Term |
| South Bank (Mesa) - Tonto National Forest - Segment B | South Bank (Mesa) - Granite Reef Trailhead to Phon D Sutton Recreation Area | Mesa | City of Mesa | USDA | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.82 | Yes | $3,523,201 | Long-Term |
| South Bank - (Mesa) - Tonto National Forest - Section 8 | South Bank (Mesa) - Phon D Sutton Recreation Area to Coon Bluff Recreation Area | Mesa | City of Mesa | USDA | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.24 | Yes | $1,550,189 | Long-Term |
| South Bank (Mesa) - Tonto National Forest - Segment C | South Bank (Mesa) - Phon D Sutton Recreation Area to Coon Bluff Recreation Area | Mesa | City of Mesa | USDA | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.24 | Yes | $1,550,189 | Long-Term |
| South Bank - (Mesa) - Tonto National Forest - Section 9 | South Bank (Mesa) - Coon Bluff Recreation Area to Water Users Recreation Site | Mesa | City of Mesa | USDA | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 8.18 | Yes | $10,218,987 | Long-Term |
| South Bank (Mesa) - Tonto National Forest - Segment D | South Bank (Mesa) - Coon Bluff Recreation Area to GoldField Recreation Area | Mesa | City of Mesa | USDA | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.1 | Yes | $2,628,788 | Long-Term |
| South Bank (Mesa) - Tonto National Forest - Segment E | South Bank (Mesa) - GoldField Recreation Area to Unnamed Trailhead | Mesa | City of Mesa | USDA | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 2.05 | Yes | $2,568,655 | Long-Term |
| South Bank (Mesa) - Tonto National Forest - Segment F | South Bank (Mesa) - Unnamed Trailhead to Sheep's Crossing Recreation Site | Mesa | City of Mesa | USDA | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.77 | Yes | $2,212,595 | Long-Term |
| South Bank (Mesa) - Tonto National Forest - Segment G | South Bank (Mesa) - Sheep's Crossing Recreation Site to Pebble Beach Recreation Area | Mesa | City of Mesa | USDA | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 0.93 | Yes | $1,160,038 | Long-Term |
| South Bank (Mesa) - Tonto National Forest - Segment H | South Bank (Mesa) - Pebble Beach Recreation Area to Water Users Recreation Site | Mesa | City of Mesa | USDA | Multi-Use Pathway | South Bank | 12 FT Wide | Concrete | 1.32 | Yes | $1,648,911 | Long-Term |
Funding Strategies
Implementation of trail and multi-use path improvements on a regional scale will likely require a combination of federal, state, regional, local, and partnership funding, often referred to as capital stacking. Participating agencies should maintain flexibility in how projects are packaged and funded, recognizing that individual funding programs may support design, construction, safety improvements, trail amenities, or related infrastructure.
Nationally, a growing number of municipalities have collectively developed policies and partnership agreements for trail and path networks provided regionally. They have also developed strong partnerships that are fair and equitable in the delivery of services, monitoring, and maintenance.
Given the multi-jurisdictional nature of this study, some policies and management practices are already in place or being considered by some agencies. The following funding sources should be considered as projects identified through the Rio Reimagined Active Transportation Study advance toward implementation.
The federal Transportation Alternatives (TA) Set-Aside is one of the most directly applicable funding sources for trail and multi-use path improvements. Eligible activities include pedestrian and bicycle facilities, recreational trails, Safe Routes to School projects, and certain environmental mitigation activities associated with transportation projects.
Within the Maricopa Association of Governments (MAG) region, agencies pursue TA funding through MAG rather than the statewide Arizona Department of Transportation (ADOT) competitive process. Projects should therefore be coordinated with MAG and positioned within applicable regional planning and programming processes.
TA funding is particularly appropriate for construction of shared-use paths, bicycle and pedestrian connections, gap closures, crossings, and improvements connecting trails to the surrounding transportation network.
MAG should be an important funding and implementation partner for projects that contribute to the regional active transportation network. Agencies should monitor MAG calls for projects and regional transportation programming opportunities that may support bicycle and pedestrian improvements.
MAG’s Active Transportation Design Assistance Program can also help member agencies advance projects toward implementation by funding feasibility evaluation and preliminary engineering/conceptual design. This can be particularly valuable for projects identified through this Study that have strong regional benefits but require additional project development before they are competitive for construction funding.
Agencies should use these opportunities strategically to move priority projects through the project-development pipeline, with early planning or design assistance establishing the foundation for subsequent construction grant applications.
The Recreational Trails Program (RTP), administered in Arizona through Arizona State Parks and Trails, provides federal funding specifically for recreational trail projects. Non-motorized projects can include development and improvement of trails and associated trail facilities.
RTP may be particularly applicable to Rio Reimagined projects where the primary function or character of the facility is recreational trail use rather than an on-street transportation facility. The program can also provide an opportunity to fund trail-specific elements that may be difficult to fund through traditional transportation programs.
For the 2026 funding cycle, Arizona’s non-motorized RTP program offered awards up to $150,000, making the program particularly useful for smaller projects, discrete trail improvements, or as one component of a larger funding package.
The Arizona State Parks and Trails Heritage Fund provides another potential source for non-motorized trails and outdoor recreation improvements. Eligible activities include development and maintenance of non-motorized trails and trail-related facilities. State, tribal, county, and local governments, among other entities, can be eligible applicants.
Heritage Fund opportunities may be particularly well suited to trail development, rehabilitation, trailheads, access improvements, and other facilities that have a strong recreational component. Agencies should monitor annual appropriations and calls for projects because available funding and program requirements may vary by funding cycle.
The U.S. Department of Transportation’s Safe Streets and Roads for All (SS4A) program can support bicycle and pedestrian infrastructure when improvements address documented roadway safety needs and are consistent with an eligible comprehensive safety action plan.
For Rio Reimagined, SS4A may be particularly applicable where multi-use paths, protected connections, intersection improvements, or crossings address safety risks for people walking and bicycling. Projects connecting a trail across or along high-speed or high-volume roadways may be especially appropriate candidates when the safety need is clearly demonstrated.
Rather than presenting a project solely as a recreational trail, agencies pursuing safety funding should demonstrate how the improvement separates vulnerable road users from traffic, addresses a documented safety problem, or provides a safer connection within the transportation network.
Congestion Mitigation and Air Quality Improvement (CMAQ) funding can support transportation projects that contribute to improved air quality in eligible areas. MAG administers regional programming of CMAQ funds within the Maricopa region.
Bicycle and pedestrian improvements may be candidates where agencies can demonstrate that the project supports transportation trips that would otherwise be made by automobile and produces an eligible air-quality benefit. Multi-use paths connecting residential areas with employment centers, transit, schools, commercial areas, or other everyday destinations may therefore be stronger candidates than facilities designed principally for recreation.
Agencies should coordinate with MAG regarding current program eligibility, project evaluation criteria, and funding availability before advancing a project specifically for CMAQ funding.
Local funding will remain an important component of trail implementation, particularly for project development, local grant matches, smaller improvements, and projects that can be incorporated into existing capital programs.
Agencies should consider programming priority trail and multi-use path improvements within their capital improvement programs. Local transportation, parks, streets, and other applicable capital funds can be used either to deliver projects directly or to provide the local commitment necessary to leverage larger state and federal awards.
Local funds can also be strategically directed toward preliminary engineering, environmental work, right-of-way, and other preconstruction activities that make a project more competitive for future grant funding.
Trail and multi-use path improvements should also be implemented opportunistically through planned roadway, bridge, and intersection projects. When a planned capital project overlaps a recommended active transportation connection, agencies should evaluate whether the trail or path can be incorporated into the larger project scope.
This approach may allow portions of an active transportation project to be funded through an existing capital project rather than requiring a stand-alone grant. It can also reduce costs by coordinating design, mobilization, drainage, utility relocation, structures, and other improvements.
Agencies should therefore routinely compare the recommended Rio Reimagined active transportation network with their 5- and 10-year capital improvement programs.
Because portions of the Rio Reimagined active transportation network may parallel waterways, drainage corridors, or flood-control facilities, coordination with the Flood Control District of Maricopa County and other drainage agencies should be pursued where projects overlap.
The Flood Control District maintains partnership programs through which eligible agencies can share costs for qualifying flood-control improvements. These programs should not be viewed as direct trail funding; rather, they may create opportunities to coordinate trail improvements with eligible drainage or flood-control projects.
For example, if a drainage project requires grading, access improvements, crossings, or reconstruction along a corridor where a planned multi-use path is also proposed, agencies should evaluate whether the projects can be designed and constructed in coordination. This approach can reduce duplication and allow each partner’s funding to support eligible portions of a combined project.
Where new development or redevelopment occurs adjacent to planned active transportation corridors, agencies should evaluate opportunities to construct trail segments, connections, easements, or related improvements as part of development.
Depending on applicable local policies and development requirements, these improvements may be delivered through development agreements, infrastructure requirements, right-of-way or easement dedication, or other negotiated partnerships.
Private and institutional partners may also provide funding or in-kind assistance for trail amenities, connections, landscaping, or other improvements where projects directly serve major destinations or development areas.
Projects that cross jurisdictional boundaries should be considered strong candidates for joint funding strategies. Two or more jurisdictions may contribute local funds, divide project-development responsibilities, or identify a single lead agency to pursue regional, state, or federal funding on behalf of the larger project.
This approach is particularly valuable for Rio Reimagined because the usefulness of a trail or multi-use path does not stop at a jurisdictional boundary. Demonstrating commitments from multiple agencies can reinforce the regional significance of a project and show funding agencies that there is institutional support for implementation and long-term maintenance.
Municipal bonds can be issued to finance trail and path projects. These bonds are backed by the government and typically repaid using tax revenues or user fees associated with the facility. Bond financing allows for large-scale projects that may require significant upfront investment that address needs that are identified as unmet community priorities.
Many parks and recreation systems add a capital improvement fee onto an existing user fee when they develop or enhance major recreation facilities. This is usually applied to amenities like trailheads and special-use facilities. The dollars gained either offset the cost of the capital improvement or the revenue bond that was used to develop or enhance the special use facility. Once the capital improvement is paid off, the fee typically expires and is discontinued.
It is important to note that the suitability of these funding strategies can vary depending on the specific project, location, and available resources. A comprehensive funding strategy may involve a combination of these approaches to ensure the successful implementation and long-term sustainability of parks and recreation projects.
Parks and recreation projects can seek corporate sponsorships to secure funding. In exchange for financial support, sponsors may receive branding opportunities, advertising exposure, or other promotional benefits.
Parks and recreation projects can often qualify for government grants from federal, state, and local agencies. These grants are typically awarded based on the project’s alignment with specific criteria, such as connectivity, safe routes, community impact, environmental sustainability, or economic development. The agency can continue to mine for additional grant funding opportunities.
Impact fees are charges imposed on new developments to mitigate the impacts they have on the community, such as increased demand for parks and recreation facilities. These fees are typically collected by the agency and used to fund the construction or expansion of infrastructure like trails and paths.
This is a fund dedicated exclusively for a park system’s maintenance and is funded by a percentage of user fees from programs, events, and rentals. The fee is paid by users and is added to a dedicated fund for facility and equipment replacement.
Partnerships are joint-development funding sources or operational funding sources formed between separate agencies, such as two government entities, a non-profit, a public agency, or a private business and a public agency. Partners jointly develop revenue-producing parks and recreation facilities and may share risk, operational costs, responsibilities, and asset management based on the strengths of each partner. In this approach, entities may provide funding or resources in exchange for specific benefits, such as naming rights, advertising opportunities, or revenue-sharing agreements.
Existing partnership agreements should be updated regularly to ensure the purpose of the partnership, what is being provided, and the terms of the agreement are accurate. New partnerships should be forged as the Department continues to evolve and modernize the parks and recreation system to align with community needs. Ensure that partnerships are fair and equitable to the Department and to the partner with the best interests of the community prioritized.
A preservation tax could be put in place to help fund the acquisition of land around scenic vistas and natural resources. The ability to take advantage or the region’s open space and natural resources was continuously cited as a priority during the community engagement portion of this plan.
Non-profit organizations, foundations, and individual donors can contribute funds to support parks and recreation projects. These donations are often made in the form of grants, sponsorships, or endowments. Philanthropic donations can be essential for funding projects that benefit specific communities or have a social or environmental focus.
Parks and recreation facilities often generate revenue through user fees, membership fees, rentals, concessions, or program charges. These user fees can help offset the operational and maintenance costs associated with the facilities.
This is an indirect revenue source consisting of individuals donating their time to assist the Department in providing a product or service on an hourly basis. This reduces the agency’s cost to provide services, builds department advocacy, and promotes civic involvement.
Recommendation Dashboard
Corridor Segment Prioritization
This content is currently available on desktop devices only. Please use a desktop or larger-screen device to access it.
| Category | Recommended Action | Implementation Strategy | Property Owners | APN | Acquisition / Easement / Intergovernmental Agreement (IGA) | Potential Lead | Supporting Partners | Performance Measure | Priority | |
|---|---|---|---|---|---|---|---|---|---|---|
| Planning or Planning Collaboration | Establish a unified regional vision and implementation framework. Develop and maintain a coordinated long-term implementation strategy that aligns investments, policies, and priorities among participating jurisdictions, tribal communities, regional agencies, and major stakeholders throughout the Rio Reimagined corridor. | Prepare and maintain a corridor-wide implementation strategy that coordinates regional priorities, policies, projects, and investments. | N/A | N/A | N/A | Rio Reimagined leadership | Participating jurisdictions; tribal communities; MAG; regional agencies | Implementation framework adopted and regularly updated | On-Going | |
| Planning or Planning Collaboration | Strengthen regional partnerships. Formalize partnerships among municipalities, tribal governments, state and federal agencies, utility providers, flood control agencies, non-profit organizations, and private landowners to advance implementation, funding, and stewardship initiatives. | Formalize coordination among municipalities, tribal governments, public agencies, utilities, nonprofit organizations, and private landowners. | N/A | N/A | N/A | Rio Reimagined leadership | Federal, state, regional, tribal, and local partners | Number of formal agreements and active partnerships | On-Going | |
| Planning or Planning Collaboration | Establish a dedicated implementation entity. Establish a Rio Reimagined governance structure or implementation organization responsible for coordinating funding, project delivery, partnership development, public outreach, and Long-Term corridor management. | Evaluate and establish an organizational structure responsible for coordination, fundraising, advocacy, project delivery, and corridor stewardship. | N/A | N/A | N/A | Rio Reimagined leadership | Participating jurisdictions; regional partners | Implementation entity established and operational | Short-Term | |
| Planning or Planning Collaboration | Develop corridor-wide design, branding, and wayfinding standards. Develop a unified Rio Reimagined identity, branding strategy, and interpretive framework that creates a consistent user experience across the entire corridor. | Adopt consistent design criteria for pathways, trailheads, signs, interpretive elements, furnishings, and gateway features. | N/A | N/A | N/A | Rio Reimagined leadership | Municipalities; tribal communities; MAG; arts and cultural partners | Regional standards completed and adopted | Short-Term | |
| Planning or Planning Collaboration | Utilize Rio Reimagined Capital Improvement Program (CIP). Utilize the coordinated capital improvement program that leverages local, regional, state, federal, and private funding sources while prioritizing projects that provide the greatest connectivity and community benefits. | Implement the priority projects, based on the identified estimated costs, implementation phases, funding sources, and responsible agencies. | N/A | N/A | N/A | Rio Reimagined leadership | Participating jurisdictions; MAG; funding agencies | Capital improvement program adopted and funded | On-Going | |
| Planning or Planning Collaboration | Implement pilot and demonstration projects. Advance highly visible demonstration projects that showcase the Rio Reimagined vision, generate public support, and position future phases for funding and implementation. | Advance highly visible, readily implementable projects that demonstrate the corridor vision and build public support. | N/A | N/A | N/A | Participating jurisdictions | Rio Reimagined leadership; landowners; nonprofit partners | Number of pilot projects completed | Short-Term | |
| Planning or Planning Collaboration | Promote equitable access and community investment. Prioritize investments that improve access to parks, trails, recreation opportunities, and transportation facilities in underserved and historically underrepresented. | Prioritize improvements that address gaps in access to trails, parks, transit, open space, and recreation opportunities. | N/A | N/A | N/A | Participating jurisdictions | Community organizations; tribal communities; public health partners | Investments completed in underserved areas | On-Going | |
| Planning or Planning Collaboration | Establish performance monitoring and reporting. Establish measurable performance metrics to monitor implementation progress, system connectivity, environmental improvements, recreational use, economic benefits, and community health outcomes. | Develop a regional monitoring program and publish regular progress reports on implementation outcomes. | N/A | N/A | N/A | Rio Reimagined leadership | Participating jurisdictions; MAG; research partners | Performance dashboard established and regularly updated | On-Going | |
| Planning or Planning Collaboration | Develop river-oriented planning and development standards. Strengthen connections between adjacent development and the river corridor through improved public access, trail connectivity, building and site orientation, compatible land uses, landscaping, and integration of public open space. | Encourage future development to provide public access, trail connections, open-space frontage, and preserved views toward the river corridor. | N/A | N/A | N/A | Participating jurisdictions | Developers; landowners; planning agencies | Standards incorporated into local plans and ordinances | On-Going | |
| Planning or Planning Collaboration | Coordinate corridor programming and activation. Encourage community events, recreational activities, educational programs, and other initiatives that increase use of the corridor, strengthen connections to surrounding communities, and promote Long-Term visibility and stewardship. | Establish a regional calendar of recreation, education, cultural, and stewardship activities. | N/A | N/A | N/A | Rio Reimagined leadership | Municipalities; tribal communities; nonprofit and cultural organizations | Number and geographic distribution of annual programs | On-Going | |
| Segment - Pathway Projects and Active Transportation Projects | Complete a continuous regional shared-use pathway network. Develop a continuous system of multi-use pathways along the Salt, Gila, and Agua Fria Rivers that eliminates gaps and provides seamless regional connectivity. | Design and construct new and missing pathway segments along the Salt, Gila, and Agua Fria Rivers. | N/A | N/A | N/A | Participating jurisdictions | MAG; flood control agencies; landowners; tribal communities | Miles of pathway completed | On-Going | |
| Segment - Pathway Projects and Active Transportation Projects | Eliminate jurisdictional pathway gaps. | Prioritize projects that connect existing facilities across municipal, tribal, and agency boundaries. | Participating jurisdictions | MAG; adjacent jurisdictions; regional agencies | Number of pathway gaps eliminated | Mid-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Expand active transportation connections. | Connect the river corridor to neighborhoods, schools, employment centers, parks, transit facilities, and community destinations. | Participating jurisdictions | Transit providers; school districts; employers; MAG | Number of destinations connected | Long-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Integrate the corridor with the regional trail system. | Coordinate Rio Reimagined alignments and facility standards with the MAG Regional Trail Network and local transportation plans. | MAG; participating jurisdictions | Rio Reimagined leadership; tribal communities | Connections incorporated into regional and local plans | Short-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Provide diverse pathway and trail experiences. | Develop paved shared-use paths, natural-surface trails, hiking routes, and equestrian facilities where appropriate. | Participating jurisdictions; land managers | Equestrian organizations; conservation partners; trail groups | Miles of each facility type completed | Mid-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Utilize levees and flood-control corridors. | Coordinate pathway construction within levees, drainage corridors, and maintenance access routes where compatible with flood-control operations. | Flood control agencies | Participating jurisdictions; irrigation districts; landowners | Miles of dual-purpose corridor developed | Mid-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Improve Rdway, canal, railRd, and freeway crossings. | Construct grade-separated crossings, enhanced at-grade crossings, and other safety improvements at identified barriers. | Transportation agencies | Municipalities; MAG; railRds; irrigation districts | Number of barriers addressed | Long-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Develop landmark bicycle and pedestrian bridges. | Construct strategic river crossings that connect communities and function as recognizable corridor landmarks. | Participating jurisdictions | MAG; flood control agencies; tribal communities | Number of river crossings completed | Long-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Expand first-mile and last-mile connections. | Improve pedestrian and bicycle access between the river corridor, transit stations, mobility hubs, and major destinations. | Participating jurisdictions; transit agencies | MAG; employers; property owners | Transit and destination connections completed | Mid-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Advance water-based recreation access. | Evaluate suitable river reaches and develop launch, recovery, safety, and support facilities where hydrologic and environmental conditions permit. | Land and resource management agencies | Participating jurisdictions; public safety agencies; recreation providers | Water access plan completed and facilities developed | Mid-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Old Highway 80 - Gillespie Dam Bridge to Salome Highway (Arlington) - 11.04 Miles | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Old Highway 80 - Segment A - Gillespie Dam Bridge to Desert Rose Rd - 4.00 Miles | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Old Highway 80 - Segment B - Desert Rose Rd to Cactus Rose Rd - 1.99 Miles | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Old Highway 80 - Segment C - Cactus Rose Rd to Arlington School Rd - 0.97 Miles | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Old Highway 80 - Segment D - Arlington School Rd to 319th Ave - 3.13 Miles | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Old Highway 80 - Segment E - 319th Ave to Salome Highway - 0.96 Miles | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Arlington Canal Rd - Old Highway 80 to W. Dobbins Butte Game Rd (Arlington) -2.86 Miles | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Arlington Canal Rd - Segment A - Old Highway 80 to 319th Ave - 2.09 Miles | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Arlington Canal Rd - Segment B - 319th Ave to Future South Bank Alignment - 0,77 Miles | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | 319TH Ave - 319th Ave to Old Highway 80 (Arlington) | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | 319TH Ave - 319th Ave to Old Highway 80 | Maricopa County Right-of-Way | N/A | No | Maricopa County Department of Transportation (MCDOT) | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Ultimate North Bank - 319th Ave - Johnson Rd to Citrus Ln (Buckeye / Goodyear) | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | ASLD / BLM / FCDMC / AZ Game & Fish / City of Buckeye / USA / Private | N/A | Yes | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Ultimate North Bank (Buckeye) - Segment A - 319th Ave to Johnson Rd | N/A | Yes | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - GARY PETERSON GABLE FAMILY TRUST | 40133016 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - GLADDEN FARMS INC | 40133011C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - GLADDEN FARMS INC | 40133013 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - GLADDEN FARMS INC | 40133001K | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Ultimate North Bank (Buckeye) - Segment B - North Bank - Johnson Rd to Palo Verde Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Private | N/A | Yes | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Private - GLADDEN DANIEL T/SHERRY L | 40114014B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HLM 3320 LLC | 40114014A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HLM 3320 LLC | 40114013 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - FINLEY RICHARD O/SANDRA/MICHAEL/DIANA FAM PAR | 40114021 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HLM 3320 LLC | 40114016A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HLM 3320 LLC | 40114023A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HLM 3320 LLC | 40114022 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BRUNER 155 LLC | 40114027B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HLM 3320 LLC | 40114036 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HARDISON INVESTMENTS LLC | 40114037B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HARDISON INVESTMENTS LLC | 40114037A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Ultimate North Bank (Buckeye) - Segment C - North Bank - Palo Verde Rd to Turner Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Private | N/A | Yes | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Private - HARDISON INVESTMENTS LLC | 40114054D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HARDISON INVESTMENTS LLC | 40114054A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - PALO VERDE Rd PROPERTIES LLC | 40104008B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - PALO VERDE Rd PROPERTIES LLC | 40104008C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - NARRAMORE DANIEL O/NARRAMORE VIRGINIA G TR | 40104004B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - PVGB-2004 LLC | 40104004C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Ultimate North Bank (Buckeye) - Segment D - North Bank - Turner Rd to Rooks Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | FCDMC / AZ Game & Fish | N/A | Yes | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 40105001 | IGA | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 40105007 | IGA | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 40105008 | IGA | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | AZ Game & Fish | 40105011 | IGA | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | AZ Game & Fish | 40105010 | IGA | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | AZ Game & Fish | 40103003 | IGA | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALMAT CO | 40102002D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALMAT CO | 40102009A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Ultimate North Bank (Buckeye) - Segment E - North Bank - Rooks Rd to Apache Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Private / State of Arizona | N/A | Yes | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Private - REDIGER JASON | 40040001 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - MARTINEZ LILIA | 40040009 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - A+ BUSINESS MANAGEMENT LLC | 40040008 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - RUBIO SUGHEY | 40040019 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALIFORNIA PORTLAND CEMENT CO | 40040024 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | State of Arizona | 40041002B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Ultimate North Bank (Buckeye) - Segment F - North Bank - Apache Rd to Rainbow Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Private | N/A | Yes | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Private - CEMEX CONSTRUCTION MATERIALS SOUTH LLC | 40044017 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CEMEX CONSTRUCTION MATERIALS SOUTH LLC | 40045018 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CEMEX CONSTRUCTION MATERIALS SOUTH LLC | 40043006 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - UPPAL LAND LLC | 40043003F | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BLOOM TIMOTHY K/DRUCELLA A | 40043013 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - VIZCARRA CRISTINA | 40043017 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HERNANDEZ ROBERTO P | 40043016 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - DEDECKER DUSTIN | 40043007U | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - GONZALES ARMANDO CASTRO | 40014087 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - GONZALES ARMANDO CASTRO | 40014088 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CEMEX CONSTRUCTION MATERIALS SOUTH LLC | 40014091 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BENBOW FREDRICK K | 40014004L | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BENBOW FREDRICK K | 40014004M | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - UNITED METRO MATERIALS INC | 40014009A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BUCKEYE RANCH | 40014009B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BUCKEYE RANCH | 40014010 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Ultimate North Bank (Buckeye) - Segment G - North Bank - Rainbow Rd to Verrado Way | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Private | N/A | Yes | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Private - BELOAT MINING COMPANY | 40011012B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BELOAT MINING COMPANY | 40011009B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BELOAT MINING COMPANY | 40011010B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CEMEX CONSTRUCTION MATERIALS LP | 40011007B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CEMEX CONSTRUCTION MATERIALS LP | 40011006B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BUCKEYE RANCH | 40011004C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - 2008 WECKERLY LIVING TRUST | 40002001B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Ultimate North Bank (Buckeye) - Segment H North Bank - Verrado Way to Perryville Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | USA / Private | N/A | Yes | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | United State of America | 40006011G | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - FISHER SAND & GRAVEL CO | 40006002 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -FISHER SAND & GRAVEL CO | 40006008B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -FISHER SAND & GRAVEL CO | 40006010A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -FISHER SAND & GRAVEL CO | 40006008D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -FISHER SAND & GRAVEL CO | 40005007 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -CHIQUITA DAIRY LLC | 40005006D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -SMNG LLC | 40005003C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -SMNG LLC | 40005003E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | United State of America | 40005009B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -SMNG LLC | 40005003E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Ultimate North Bank (Buckeye) - Segment I - North Bank - Perryville Rd to Citrus Ln | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Private | N/A | Yes | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Private - DESERT AGGREGATES LLC | 40005001E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - MOISES TAPIA AND BERTHA A TAPIA TRUST | 40005001D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - DESERT AGGREGATES LLC | 50257010E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HUNJAN AGRICULTURAL LLC | 50257009C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - DESERT AGGREGATES LLC | 50257009D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BOCCHICCHIO NICHOLAS | 50257014Z | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - GALINDO ESTHER/DURAN ARTEMIO BARRAGAN | 50257014B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - MENDOZA ROBERTO PEDRO | 50257014P | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - DESERT AGGREGATES LLC | 50257012D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - DESERT AGGREGATES LLC | 50257014R | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - DESERT AGGREGATES LLC | 50257012E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - DESERT AGGREGATES LLC | 50257012F | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 50257012G | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - DESERT AGGREGATES LLC | 50257018B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - DESERT AGGREGATES LLC | 50257017 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank Connector (Goodyear) - Estrella Parkway to Bullard Ave | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | FCDMC / BWDCD / Private | N/A | Yes | City of Goodyear | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | North Bank Connector (Goodyear) - Estrella Parkway to Bullard Ave | Flood Control District of Maricopa County (FCDMC) | 50081008 | Intergovernmental Agreement (IGA) | City of Goodyear | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - BWDCD | 50081007D | Intergovernmental Agreement (IGA) | City of Goodyear | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - PIONEER 2005 LLC | 50081001A | Intergovernmental Agreement (IGA) | City of Goodyear | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - PIONEER 2005 LLC | 50081007C | Intergovernmental Agreement (IGA) | City of Goodyear | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - PIONEER 2005 LLC | 50082001E | Intergovernmental Agreement (IGA) | City of Goodyear | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Buckeye Canal - Old Hwy 80 to Perryville Rd | Work with Buckeye Water Conservation Drainage District (BWCDD) to create an IGA for recreation use on the canal. Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Yes | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment A - Buckeye Canal - Buckeye canal Rd to Johnson Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment B - Buckeye Canal - Johnson Rd to Bruner Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment C - Buckeye Canal - Bruner Rd to Palo Verde Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment D - Buckeye Canal - Palo Verde Rd to Wilson Ave | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment E - Buckeye Canal - Wilson Ave to Turner Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment F - Buckeye Canal - Turner Rd to MC 85 | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment G - Buckeye Canal - MC 85 to Rooks Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment H - Buckeye Canal - Rooks Rd to Miller Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment I - Buckeye Canal - Miller Rd to Apache Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment J - Buckeye Canal - Apache Rd to Watson Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment K - Buckeye Canal - Watson Rd to Rainbow Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment L - Buckeye Canal -Rainbow Rd to Dean Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment M - Buckeye Canal - Dean Rd to Verrado Way | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment N - Buckeye Canal - Verrado Way to Jackrabbit Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (BUCKEYE) - Segment O - Buckeye Canal - Jackrabbit Rd to Perryville Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Goodyear) - Section 1 - Buckeye Canal - Perryville Rd to Estrella Parkway | Work with Buckeye Water Conservation Drainage District (BWCDD) to create an IGA for recreation use on the canal. Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Goodyear) - Segment P - Buckeye Canal - Perryville Rd to Citrus Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Goodyear) - Segment Q - Buckeye Canal - Citrus Rd to Cotton Ln | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Goodyear) - Segment R - Buckeye Canal - Cotton Ln to Sarival Ave | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Goodyear) - Segment S - Buckeye Canal - Sarival Ave to Estrella Parkway | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Goodyear) - Section 2 - Buckeye Canal - Estrella Parkway to Litchfield Rd | Work with Buckeye Water Conservation Drainage District (BWCDD) to create an IGA for recreation use on the canal. Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Goodyear) - Segment T - Buckeye Canal - Estrella Parkway to Bullard Ave | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Goodyear) - Segment U - Buckeye Canal - Bullard Ave to Litchfield Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Avondale) - Buckeye Canal - Litchfield Rd to El Mirage Rd | Work with Buckeye Water Conservation Drainage District (BWCDD) to create an IGA for recreation use on the canal. Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Avondale | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Avondale ) - Segment V - Buckeye Canal - Litchfield Rd to Vermeersch Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Avondale | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Canal (Avondale ) - Segment W - Buckeye Canal - Vermeersch Rd to El Mirage Rd | Buckeye Water Conservation Drainage District (BWCDD) | N/A | Intergovernmental Agreement (IGA) | City of Avondale | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Avondale) - Agua Fria River to El Mirage Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | FCDMC / Private | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Avondale) - North Bank - Agua Fria River to El Mirage Rd | Flood Control District of Maricopa County (FCDMC) | 50078001L | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - QUINN ENTERPRISES LP | 50078001M | Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - QUINN ENTERPRISES LP | 50078001D | Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - QUINN ENTERPRISES LP | 50078009A | Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ALLIED CONCRETE & MATERIALS CO | 50075003C | Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ALLIED CONCRETE & MATERIALS CO | 50075004C | Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ALLIED CONCRETE & MATERIALS CO | 50075005H | Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KILGORE COMPANIES LLC | 50075001C | Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | El Mirage Rd (Avondale) - Buckeye Canal to Gila River North Bank | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | El Mirage Rd - Buckeye Canal to Gila River North Bank | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Avondale) - El Mirage Rd to 107th Ave | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Flood Control District of Maricopa County (FCDMC) | N/A | Intergovernmental Agreement (IGA) | City of Avondale | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Avondale) - Segment A - El Mirage Rd to 107th Ave | Flood Control District of Maricopa County (FCDMC) | N/A | Intergovernmental Agreement (IGA) | City of Avondale | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Section 1 - 107th Ave to 7th Ave | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | FCDMC / City of Phoenix / City of Tolleson / ASLD / ADOT / BLM / Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment B - 107th Ave to 99th Ave | City of Phoenix | N/A | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | N/A | Intergovernmental Agreement (IGA) | City of Phoenix | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment C - 99th Ave to 91st Ave | City of Phoenix | N/A | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment D - 91st Ave to 83rd Ave | City of Phoenix | N/A | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Tolleson | N/A | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ASLD | N/A | Acquisition | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment E - 83rd Ave to 75th Ave | City of Phoenix | N/A | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - FLORIDA ROCK INDUSTRIES INC | 10469009B | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BCW INC | 10469002C | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BCW INC | 10469001A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - FLORIDA ROCK INDUSTRIES INC | 10470003B | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment F - 75th Ave to 67th Ave | Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - FLORIDA ROCK INDUSTRIES INC | 10470003A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - FLORIDA ROCK INDUSTRIES INC | 10468002 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALIFORNIA PORTLAND CEMENT | 10471010A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment G - 67th Ave to 59th Ave | ADOT / ASLD | N/A | Yes | City of Phoenix | ADOT | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | ADOT | N/A | Intergovernmental Agreement (IGA) | City of Phoenix | ADOT | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ASLD | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment H - 59th Ave to 51st Ave | City of Phoenix | N/A | City of Phoenix Right-of-Way | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment I - 51st Ave to 43rd Ave | City of Phoenix / Private | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10460002G | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | US Dept of Energy | 10460002C | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10460002D | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KILLGORE COMPANIES | 10461003 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment J - 43rd Ave to 35th Ave | City of Phoenix / Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10546002A | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10546003E | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - MUTLU RAMADAN H/AYSEL H | 10546003K | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10546004F | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment K - 35th Aven to 27th Ave | City of Phoenix / Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10546004F | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10549010C | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CARRILLO RECYCLE AUTO PARTS LLC | 10549004 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALIFORNIA PORTLAND CEMENT | 10550004C | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALIFORNIA PORTLAND CEMENT | 10548010B | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALIFORNIA PORTLAND CEMENT | 10548001E | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALIFORNIA PORTLAND CEMENT | 10550006 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment L - 27th Ave to 19th Ave | City of Phoenix / Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10551016B | Easement | City of Phoenix | N/A | Miles of pathway completed | Mid-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALIFORNIA PORTLAND CEMENT | 10551004A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Mid-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALIFORNIA PORTLAND CEMENT | 10552007A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Mid-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALIFORNIA PORTLAND CEMENT | 10552006E | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Mid-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10552006D | Easement | City of Phoenix | N/A | Miles of pathway completed | Mid-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10552006B | Easement | City of Phoenix | N/A | Miles of pathway completed | Mid-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment M - 19th Ave to 7th Ave | City of Phoenix | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Short-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10553013A | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10553013C | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10538008B | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10538008A | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Section 2 - 16th Street | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | City of Phoenix / Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - 16th Street | City of Phoenix | 12229003F | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Section 3 - 24th Street | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | City of Phoenix / Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - 24th Street | City of Phoenix | 12229003F | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12225002M | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12225002P | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ARIZONA SAND AND ROCK COMPANY | 12225002S | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Section 4 - 24th St to 48th St | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | City of Phoenix / State of Arizona | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment N - 24th St to 32nd St | City of Phoenix | 12225002P | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12225004H | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | State of Arizona | 12225004F | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | State of Arizona | 12224002D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | State of Arizona | 12224002N | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12224002P | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12224001J | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12141003D | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12139001F | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment O - 32nd St to 40th St | City of Phoenix | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Short-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12139001F | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12139001E | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12138006 | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12138001B | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Phoenix) - Segment P - 40th St to 48th St | City of Phoenix | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Short-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12443002C | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12443002B | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12442001 | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12441001A | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 12441001D | Easement | City of Phoenix | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Tempe) - Section 5 - 48th St to Priest Dr | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | City of Tempe / ADOT | N/A | Easement | City of Tempe | ADOT | Miles of pathway completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Tempe) - Segment Q - 48th St to Priest Dr | City of Tempe | 12478001C | Easement | City of Tempe | N/A | Miles of pathway completed | Short-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | ADOT | N/A | Intergovernmental Agreement (IGA) | City of Tempe | ADOT | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Tempe | 12420006E | Easement | City of Tempe | N/A | Miles of pathway completed | Short-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Tempe) - Section 6 - Miller Rd to Sr 101 | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | ADOT | N/A | Intergovernmental Agreement (IGA) | City of Tempe | ADOT | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | North Bank (Tempe) - Segment R - Miller Rd to Sr 101 | ADOT | N/A | Intergovernmental Agreement (IGA) | City of Tempe | ADOT | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | North Bank (SRPMIC) - Section 7 - SR101 to Alma School Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | SRPMIC | N/A | N/A | SRPMIC | N/A | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | North Bank (SRPMIC) - Segment S - SR101 to Alma School Rd | SRPMIC | N/A | N/A | SRPMIC | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Arlington) - Section 1 - Gillespie Dam to 319th Ave | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | FCDMC / BLM / ASLD / BLM / AZGFD / Private | N/A | Yes | Maricopa County | N/A | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Arlington) - Segment A - Gillespie Dam to Desert Rose Rd | Private - Paloma Irrigation and Drainage District | 40161017U | Intergovernmental Agreement (IGA) | Maricopa County | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - Paloma Irrigation and Drainage District | 40161017R | Intergovernmental Agreement (IGA) | Maricopa County | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - Paloma Irrigation and Drainage District | 40161017J | Intergovernmental Agreement (IGA) | Maricopa County | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 40161017F | Intergovernmental Agreement (IGA) | Maricopa County | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | Maricopa County | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Arizona State Land Department (ASLD) | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | Maricopa County | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | Maricopa County | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Arizona State Land Department (ASLD) | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | Maricopa County | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Arizona Game & Fish Department (AGFD) | 40160007 | Intergovernmental Agreement (IGA) | Maricopa County | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Arlington) - Segment B - Desert Rose Rd to 319 Ave | BLM / ASLD / BLM / AZGFD | N/A | Yes | Maricopa County | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Arizona Game & Fish Department (AGFD) | 40160007 | Intergovernmental Agreement (IGA) | Maricopa County | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Arizona Game & Fish Department (AGFD) | 40160008 | Intergovernmental Agreement (IGA) | Maricopa County | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Arizona Game & Fish Department (AGFD) | 40160002 | Intergovernmental Agreement (IGA) | Maricopa County | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | Maricopa County | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Arizona State Land Department (ASLD) | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | Maricopa County | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Arizona Game & Fish Department (AGFD) | 40160003 | Intergovernmental Agreement (IGA) | Maricopa County | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Arizona State Land Department (ASLD) | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | Maricopa County | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | Maricopa County | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Buckeye) - Section 2 - 319th Ave to Perryville Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | BLM / Private | N/A | Yes | City of Buckeye | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Buckeye) - Segment C - 319th Ave to Johnson Rd | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - BARRAZA JUAN D/JOSE E | 40133015 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - WARD PAUL | 40133008 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - WARD PAUL | 40133009 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Buckeye) - Segment D - Johnson Rd to Palo Verde Rd | BLM / Private | N/A | Yes | City of Buckeye | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - AMERICAN ALPHA FOXTROT 401K PSP | 40114042 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - DOWDY VIRL E/LOWELL D/KEVIN W | 40114044 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - SAWMILL FLATS PROPERTIES LLC | 40114043 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BRUNER PAUL V/JUDITH A | 40114041 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - WAN MELODY X | 40114049 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Buckeye) - Segment E - Palo Verde Rd to Turner Rd | ASLD / BLM / AZGFD | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | State of Arizona | 40114038 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ARIZONA STATE GAME & FISH COMMISSION | 40104031 | Intergovernmental Agreement (IGA) | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ARIZONA STATE GAME & FISH COMMISSION | 40104029 | Intergovernmental Agreement (IGA) | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ARIZONA STATE GAME & FISH COMMISSION | 40104028 | Intergovernmental Agreement (IGA) | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ARIZONA STATE GAME & FISH COMMISSION | 40104030 | Intergovernmental Agreement (IGA) | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ARIZONA STATE GAME & FISH COMMISSION | 40104027 | Intergovernmental Agreement (IGA) | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Buckeye) - Segment F - Turner Rd to Rooks Rd | SRPMIC / AZGFD / Private | N/A | Yes | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | ARIZONA STATE GAME & FISH COMMISSION | 40104026 | Intergovernmental Agreement (IGA) | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ARIZONA STATE GAME & FISH COMMISSION | 40104025 | Intergovernmental Agreement (IGA) | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ARIZONA STATE GAME & FISH COMMISSION | 40104023 | Intergovernmental Agreement (IGA) | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ARIZONA STATE GAME & FISH COMMISSION | 40104015D | Intergovernmental Agreement (IGA) | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - PHOENIX CEMENT COMPANY | 40104018B | Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | SRPMIC | 40046021 | Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Buckeye) - Segment G - Rooks Rd to Apache Rd | ASLD / BLM / SRPMIC / FCDMC / USA / Private | N/A | Yes | City of Buckeye | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - MITROVICH LOU/MARIA | 40046016C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | SRPMIC | 40046022 | Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - A & B SILICA SAND INC | 40046008A | Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KAIBAB LLC | 40046002A | Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 40046002B | Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | United States of America | 40046009 | Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Buckeye) - Segment H - Apache Rd to Rainbow Rd | ASLD / State of Arizona / Private | N/A | Yes | City of Buckeye | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | ASLD | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | State of Arizona | 40049008 | Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - WILEY GENEE | 40049007D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - WILEY GENEE | 40049007C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ACKA NO 7 LIMITED PARTNERSHIP | 40049004E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - POPENOE ROSS/FORHAN ERICA | 40049004B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - SANTANA BENJAMIN A | 40049001C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BATIE FAMILY TRUST | 40049001E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - SANTO TOMAS LLC | 40049001H | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - FELICITY FLEET LLC | 40049001R | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Buckeye) - Segment I - Rainbow Rd to Verrado Way | BLM / AZGFD / FCDMC / Private | N/A | Yes | City of Buckeye | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ACKA 7 LIMITED PARTNERSHIP | 40050013A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ACKA 7 LIMITED PARTNERSHIP | 40050013B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ACKA 7 LIMITED PARTNERSHIP | 40050015 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - MONTERRA DEVELOMENT LTD | 40050008A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - MONTERRA DEVELOMENT LTD | 40050009C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ARIZONA STATE GAME & FISH COMMISSION | 40011008H | Intergovernmental Agreement (IGA) | City of Buckeye | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - THE BROTHERS FOUR | 40002004A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 40002004B | Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 40002003G | Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 40002003J | Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - SPERANZA LINDA M | 40002002A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - BENAVIDEZ CUAUHTEMOC OROZCO | 40002008G | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ROJAS-MALDONADO CLEMENTE | 40002008F | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ANN CAMPBELL DECLARATION OF LIVING TRUST | 40002007 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Buckeye) - Segment J - Verrado Way to Perryville Rd | BLM / ASLD / BLM / FCDMC / Private | N/A | Yes | City of Buckeye | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 40008017C | Intergovernmental Agreement (IGA) | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - WAGNER ROBERT W & SCP CONSTRUCTION | 40008017B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ROBERT M WAGNER LIVING TRUST | 40008001A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ASLD | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HUNJAN AGRICULTURAL LLC | 40007001B | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - HUNJAN PROPERTIES LLC | 40007005 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ASLD | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Goodyear) - Segment K - Perryville Rd to Citrus Ln | ASLD / Private | N/A | Yes | City of Buckeye | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | ASLD | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 40004003C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ASLD | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 40004005D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 40004006F | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ASLD | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Goodyear) - Segment L - South Bank (Goodyear) - Citrus Ln to Sarival Rd | Private | N/A | Yes | City of Goodyear | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 40003002D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 40003002C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 40003001S | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 50085005F | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 50085004G | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 50085004H | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 50085004D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 50086003D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Goodyear) - Segment M - Sarival Rd to Bullard Ave | Private | N/A | Yes | City of Goodyear | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 50086003E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - KR TIC 1 LLC/KR TIC 2 LLC | 50086002M | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Goodyear / Avondale) - Section 3 - Bullard Ave to Avondale Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | MARICOPA COUNTY BOARD OF SUPERVISORS / BWCDD | N/A | Yes | City of Goodyear / City of Avondale | N/A | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Goodyear) - Segment N - Bullard Ave to Litchfield Rd | MARICOPA COUNTY BOARD OF SUPERVISORS | 50082002A | Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | MARICOPA COUNTY BOARD OF SUPERVISORS | 50079007A | Intergovernmental Agreement (IGA) | City of Goodyear | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Water Conservation Drainage District (BWCDD) | 50099001B | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Water Conservation Drainage District (BWCDD) | 50079002B | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Water Conservation Drainage District (BWCDD) | 50079012A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Water Conservation Drainage District (BWCDD) | 50079012B | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Avondale) - Segment O - Litchfield Rd to El Mirage Rd | FCDMC / BLM / Private | N/A | Yes | City of Avondale | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 50078002F | Intergovernmental Agreement (IGA) | City of Avondale | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 50078003 | Intergovernmental Agreement (IGA) | City of Avondale | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - SPARTAN INDUSTRIES LLC | 50078005D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - SPARTAN INDUSTRIES LLC | 50078006D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - SPARTAN INDUSTRIES LLC | 50078010E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | Intergovernmental Agreement (IGA) | City of Avondale | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | Private - PHOENIX SPEEDWAY CORP | 40001008E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | Intergovernmental Agreement (IGA) | City of Avondale | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Avondale) - Segment P - El Mirage Rd to Avondale Rd | FCDMC / State of Arizona / Private | N/A | Yes | City of Avondale | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - PHOENIX SPEEDWAY CORP | 40001181 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - PHOENIX SPEEDWAY CORP | 50069101A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 50069081B | Intergovernmental Agreement (IGA) | City of Avondale | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - PHOENIX SPEEDWAY CORP | 50069101A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - PHOENIX SPEEDWAY CORP | 50069081C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | State of Arizona | 50069001R | Intergovernmental Agreement (IGA) | City of Avondale | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Avondale / Phoenix) - Section 4 - Avondale Rd to 15th Ave | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | AZGFD / FCDMC | N/A | Yes | City of Avondale / City of Phoenix | N/A | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Avondale) - Segment Q - Avondale Rd to 107th Ave | ARIZONA STATE GAME & FISH COMMISSION | 10144023 | Intergovernmental Agreement (IGA) | City of Avondale | Arizona Game & Fish Department (AGFD) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 10147003 | Intergovernmental Agreement (IGA) | City of Avondale | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Phoenix) - Segment R - 107th Ave to 99th Ave | Flood Control District of Maricopa County (FCDMC) | 10147003 | Intergovernmental Agreement (IGA) | City of Phoenix | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Phoenix) - Segment S - 99th Ave to 83rd Ave | Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10150007A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10150006 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10150005 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10150003 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10151001 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10151002 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10151003 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10151005A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10484002G | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Phoenix) - Segment T - 83rd Ave to 67th Ave | ASLD / FCDMC / Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10484013T | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10484002D | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10484002G | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | FLORIDA ROCK INDUSTRIES INC | 10484004 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ALTA VISTA LUWANNA LLC | 10484001C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | M & J MOLINA FAMILY TRUST | 10484001D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ASLD | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||||
| Segment - Pathway Projects and Active Transportation Projects | BCW INC | 10469002C | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | BCW INC | 10469001A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | BCW INC | 10470001 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | BCW INC | 10470004A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | CTI INC | 10470004J | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | BCW INC | 10470004F | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | BCW INC | 10470004D | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | BCW INC | 10470002D | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | BCW INC | 10470002C | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ERMAN AND MAUREEN CHRISTOFFERSON LIVING TRUST | 10471002 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ERMAN AND MAUREEN CHRISTOFFERSON LIVING TRUST | 10471004D | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ERMAN AND MAUREEN CHRISTOFFERSON LIVING TRUST | 10471004E | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ERMAN AND MAUREEN CHRISTOFFERSON LIVING TRUST | 10471008 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ZAVALA BUCKEYE PROPERTY LLC | 10471005C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | MARINKOVIC SVETLANA | 10471009 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | MCLAWS TROY LEON | 10471006 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | LATHGANI MOE | 10471007C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 10471007D | Intergovernmental Agreement (IGA) | City of Phoenix | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Flood Control District of Maricopa County (FCDMC) | 10471007T | Intergovernmental Agreement (IGA) | City of Phoenix | Flood Control District of Maricopa County (FCDMC) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Phoenix) - Segment U - 67th Ave to 51st Ave | SRPMIC / BLM / ASLD / Private / City of Phoenix | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | SRPMIC | 10472002B | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Phoenix | Bureau of Land Management (BLM) | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | ASLD | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CEMEX CONS MATERIALS SOUTH LE # 04-105164 | 10464003A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - ARIZONA SAND AND ROCK COMPANY | 10464001A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix ROW | N/A | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Phoenix) - Segment V - 51st Ave to 35th Ave | City of Phoenix / Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Private - CALMAT COMPANY | 10463004S | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10463002 | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10460002D | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10461001 | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10546002A | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10546003E | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - MUTLU RAMADAN H/AYSEL H | 10546003K | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10546004F | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Phoenix) - Segment W - 35th Ave to 15th Ave | City of Phoenix / Private | N/A | Yes | City of Phoenix | N/A | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix | 10549010C | Easement | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private - CARRILLO RECYCLE AUTO PARTS LLC | 10549004 | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -CALIFORNIA PORTLAND CEMENT COMPANY | 10550004C | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -CALIFORNIA PORTLAND CEMENT COMPANY | 10548010B | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -CALIFORNIA PORTLAND CEMENT COMPANY | 10548001E | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -CALIFORNIA PORTLAND CEMENT COMPANY | 10548008E | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -CALIFORNIA PORTLAND CEMENT COMPANY | 10551005A | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -CALIFORNIA PORTLAND CEMENT COMPANY | 10551007 | Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -VILLAGOMEZ JOSE A II/HECTOR H | 10551003A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | Private -CALIFORNIA PORTLAND CEMENT COMPANY | 10552009H | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | City of Phoenix ROW | N/A | N/A | City of Phoenix | N/A | Miles of pathway completed | Long-Term | |||
| Segment - Pathway Projects and Active Transportation Projects | South Bank - (Mesa) - South Canal - Section 5 - Alma School Rd to Center St | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Salt River Project (SRP) | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Salt River Project (SRP) | Miles of pathway completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - South Canal - Segment A - Alma School Rd to Center St | Salt River Project (SRP) | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Salt River Project (SRP) | Miles of pathway completed | Short-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank - (Mesa) - South Canal - Section 6 - Mesa Dr to Power Rd | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Salt River Project (SRP) | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Salt River Project (SRP) | Miles of pathway completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - South Canal - Segment B - Mesa Dr to Gilbert Rd | Salt River Project (SRP) | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Salt River Project (SRP) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - South Canal - Segment C - Mesa Dr to Gilbert Rd | Salt River Project (SRP) | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Salt River Project (SRP) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - South Canal - Segment D - Gilbert Rd to Val Vista Dr | Salt River Project (SRP) | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Salt River Project (SRP) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - South Canal - Segment E - Higley Rd to Power Rd | Salt River Project (SRP) | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Salt River Project (SRP) | Miles of pathway completed | Mid-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank - (Mesa) - Tonto National Forest - Section 7 - South Canal to Phon D Sutton Recreation Area | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Salt River Project (SRP) / Tonto National Forest | N/A | Yes | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - Tonto National Forest - Segment A - South Canal to Granite Reef Recreation Area | Salt River Project (SRP) | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - Tonto National Forest - Segment B - Granite Reef Trailhead to Phon D Sutton Recreation Area | Tonto National Forest | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank - (Mesa) - Tonto National Forest - Section 8 - Phon D Sutton Recreation Area to Coon Bluff Recreation Area | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Tonto National Forest | N/A | Yes | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - Tonto National Forest - Segment C - Phon D Sutton Recreation Area to Coon Bluff Recreation Area | Tonto National Forest | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank - (Mesa) - Tonto National Forest - Section 9 - Coon Bluff Recreation Area to Water Users Recreation Site | Design and construct new and missing pathway segments along the Salt and Gila River Corridor. | Tonto National Forest | N/A | Yes | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - Tonto National Forest - Segment D - Coon Bluff Recreation Area to Goldfield Recreation Area | Tonto National Forest | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - Tonto National Forest - Segment E - Goldfield Recreation Area to Unnamed Trailhead | Tonto National Forest | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - Tonto National Forest - Segment F - Unnamed Trailhead to Sheep's Crossing Recreation Site | Tonto National Forest | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - Tonto National Forest - Segment G - Sheep's Crossing Recreation Site to Pebble Beach Recreation Area | Tonto National Forest | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | South Bank (Mesa) - Tonto National Forest - Segment H - Pebble Beach Recreation Area to Water Users Recreation Site | Tonto National Forest | N/A | Intergovernmental Agreement (IGA) | City of Mesa | Tonto National Forest | Miles of pathway completed | Long-Term | ||
| Segment - Pathway Projects and Active Transportation Projects | Rio Reimagined Active Transportation Projects | |||||||||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye - MC-85 - Ult North Bank to W. Southern Ave | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | Maricopa County Right-of-Way | N/A | N/A | MCDOT | N/A | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye - Rooks Rd - Ult. Gila River North Bank to Lower River Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Buckeye Right-of-Way | N/A | N/A | City of Buckeye | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye - Rooks Rd - W. MC-85 to Maricopa Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Buckeye Right-of-Way / BWCDD / UPRR | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye - Rainbow Rd - Ult. North Bank to Buckeye Canal Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Buckeye / BWCDD | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye - Rainbow Rd - Buckeye Canal Rd to BRdway Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Buckeye Right-of-Way / BWCDD / UPRR | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye - Jackrabbit Rd - W, Lower River Rd to Buckeye Canal Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Buckeye / BWCDD | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye - Jackrabbit Rd - Buckeye Canal Rd to W. Lower Buckeye Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Buckeye / BWCDD | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Buckeye Water Conservation Drainage District (BWCDD) | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Buckeye - W. Lower Buckeye Rd - Jackrabbit Rd to Perryville Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Buckeye Right-of-Way | N/A | N/A | City of Buckeye | N/A | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Goodyear - S. Estrella Parkway - Buckeye Canal to Bullard Ave | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Goodyear Right-of-Way / UPRR / BWCDD | N/A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of Bikeways and pathways completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Goodyear - S. Estrella Parkway - Buckeye Canal to Bullard Ave | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Goodyear Right-of-Way / UPRR / BWCDD | N/A | Intergovernmental Agreement (IGA) | City of Goodyear | Buckeye Water Conservation Drainage District (BWCDD) | Miles of Bikeways and pathways completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Goodyear - S. Estrella Parkway - UPRR - W. Goodyear Blvd South | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Goodyear Right-of-Way | N/A | N/A | City of Goodyear | N/A | Miles of Bikeways and pathways completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Goodyear - S. Estrella Parkway - W. Lower Buckeye Pkwy - W. Goodyear Blvd South | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Goodyear Right-of-Way | N/A | N/A | City of Goodyear | N/A | Miles of Bikeways and pathways completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Goodyear - S. Estrella Parkway - Goodyear Blvd South to Goodyear Blvd North | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Goodyear Right-of-Way | N/A | N/A | City of Goodyear | N/A | Miles of Bikeways and pathways completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Goodyear - S. Estrella Parkway - Goodyear Blvd South to Goodyear Blvd North | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Goodyear Right-of-Way | N/A | N/A | City of Goodyear | N/A | Miles of Bikeways and pathways completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Goodyear - S. Sarival Ave - Dunlap Rd to W. Yuma Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Goodyear Right-of-Way | N/A | N/A | City of Goodyear | N/A | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Goodyear - S. Cotton Ln - W. Estrella Pkwy to MC-85 | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Goodyear Right-of-Way | N/A | N/A | City of Goodyear | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Goodyear - S. Cotton Ln - W. Estrella Pkwy to MC-85 | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Goodyear Right-of-Way | N/A | N/A | City of Goodyear | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Goodyear - W. Lower Buckeye Rd - S. Cotton Ln to Citrus Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Goodyear Right-of-Way | N/A | N/A | City of Goodyear | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Avondale - S. Avondale Rd - El Mirage Rd to W. Lower Buckeye Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Avondale - S. Avondale Rd - Bridge | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Avondale - S. El Mirage Rd - Indian Springs Rd to BRdway Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Avondale - S. El Mirage Rd - BRdway Rd to Durango St | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Avondale - S. El Mirage Rd - Lower Buckeye Rd to Durango St. | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Avondale - S. Dysart Rd - Buckeye Canal Rd to W. Lower Buckeye Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Avondale - S. Dysart Rd - Ult. North Bank to Buckeye Canal Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Avondale - S. Litchfield Rd - W. BRdway Rd. to Lower Buckeye Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Avondale - S. Litchfield Rd (Alignment) - Ult. North Bank (Southern Ave Alignment) to Lower Buckeye Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Private - Pioneer 2005 LLC | 50077001C | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Avondale | N/A | |||||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Water Conservation Drainage District (BWCDD) | 50077002E | Intergovernmental Agreement (IGA) | City of Avondale | Buckeye Water Conservation Drainage District (BWCDD) | |||||
| Segment - Pathway Projects and Active Transportation Projects | Buckeye Water Conservation Drainage District (BWCDD) | 50080003C | Intergovernmental Agreement (IGA) | City of Avondale | Buckeye Water Conservation Drainage District (BWCDD) | |||||
| Segment - Pathway Projects and Active Transportation Projects | Avondale - W. Lower Buckeye Rd - Litchfield Rd to Dysart Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Avondale - W. Lower Buckeye Rd - El Mirage Rd to 107th Ave | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Avondale Right-of-Way | N/A | N/A | City of Avondale | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 91st Ave - W. Baseline Rd to W. BRdway Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 91st Ave - W. Lower Buckeye Rd to W. Pima Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 67th Ave - W. Southern Ave to Buckeye Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 51st Ave - W. Olnly Ave to W. South Mountain Ave | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 51st Ave - South of W. Baseline Rd to South of W. Maldonado Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 51st Ave - W. BRdway Rd Bridge | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 35th Ave - W. Dobbins Rd to Cesar Chavez Park Dr | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 35th Ave - Cesar Chavez Park Dr to W. Buckeye Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 35TH Ave - W. Buckeye Rd to Roosevelt St | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 19th Ave - W. Southern Ave to MLK JR Blvd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 19th Ave - MLK JR. Blvd to I-10 | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 7th Ave - Mohave St to McDowell Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 7th St - North of E. Victory St to E. University Dr (Bridge) | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 7th St - North of E. Watkins St to E. Apache St | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 16th St - E. Baseline Rd to I-17 | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 16th St - I-17 to Washington | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 16th St. - E. Roosevelt St to E. McDowell Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Phoenix - S. 24th St - E. Baseline Rd to Magnolia St | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Phoenix Right-of-Way | N/A | N/A | City of Phoenix | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Tempe - N. Priest Rd - Rio Salado Pkwy to W. Washington St | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Tempe - Right-of-Way | N/A | N/A | City of Tempe | N/A | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Tempe - N. Mill Ave - Gammage Pkwy to E. Curry Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Tempe - Right-of-Way | N/A | N/A | City of Tempe | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Tempe - N. Rural Rd - US-60 to E. Curry Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Tempe - Right-of-Way | N/A | N/A | City of Tempe | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Tempe - E. Curry Rd - N. Scottsdale Rd to McClintock Dr | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Tempe - Right-of-Way | N/A | N/A | City of Tempe | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Tempe - S. McClintock Dr - Apache Blvd to Loop 202 (North Side) | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Tempe - Right-of-Way | N/A | N/A | City of Tempe | N/A | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Mesa - S. Dobson Rd - W. Southern Ave to N. Mesa Riverview Dr | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Mesa Right-of-Way | N/A | N/A | City of Mesa | N/A | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Mesa - N. Center St - E. McKellips Rd to W. Lehi Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Mesa Right-of-Way | N/A | N/A | City of Mesa | N/A | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Mesa - N. Val Vista - E. Brown Rd to Loop 202 (North) | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Mesa Right-of-Way | N/A | N/A | City of Mesa | N/A | Miles of Bikeways and pathways completed | Mid-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Mesa - N. Power Rd - E. McDowell Rd to N. Bush Hwy | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Mesa Right-of-Way | N/A | N/A | City of Mesa | N/A | Miles of Bikeways and pathways completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Mesa - N. Bush Hwy - Power Rd to Saguaro Lake | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | MCDOT Right-of-Way | N/A | N/A | MCDOT | N/A | Miles of Bikeways and pathways completed | Long-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Mesa - E. Thomas Rd - Power Rd to N. Recker Rd | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | City of Mesa Right-of-Way | N/A | N/A | City of Mesa | N/A | Miles of Bikeways and pathways completed | Short-Term | |
| Segment - Pathway Projects and Active Transportation Projects | Mesa - Salt River Sand & Rock Rd - Higley Rd to South Canal | Design and construct new and missing Active Transportation Projects including - bikeways and multi-use pathway segments along the identified priority corridors. | Private | N/A | N/A | City of Mesa | N/A | Miles of Bikeways and pathways completed | Short-Term | |
| Trailheads and Amenities | Develop a trailhead hierarchy. Establish a trailhead classification system based on location, access, anticipated use, and appropriate levels of amenities and services. | Identify regional, community, and neighborhood trailhead locations based on access, demand, available land, and corridor function. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Rio Reimagined leadership | Trailhead master plan completed | Short-Term | |
| Trailheads and Amenities | Develop signature trailheads and gateways. Establish a network of trailheads and gateway destinations that create identifiable access points and serve as hubs for recreation, education, and community gathering. | Construct high-visibility trailheads and gateway features at major corridor access points. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Rio Reimagined leadership; landowners | Number of signature trailheads completed | Mid-Term | |
| Trailheads and Amenities | Enhance and expand the existing Historic Gillespie Dam Bridge parking area, currently maintained by MCDOT, to serve as a formal trailhead supporting access to the historic bridge, dam ruins, and regional trail system. Improvements should include expanded parking, visitor amenities, and interpretive features that enhance access, safety, and the overall visitor experience. | Construct high-visibility trailheads and gateway features at major corridor access points. | MCDOT Right-of-Way | N/A | N/A | MCDOT | Rio Reimagined leadership; landowners | Number of signature trailheads completed | Mid-Term | |
| Trailheads and Amenities | Develop a new trailhead at the Arlington Wildlife Area to serve as a multimodal access hub connecting the proposed Rio Reimagined North Bank Trail, South Bank Trail, and riverbed trail system. The trailhead should include visitor amenities, wayfinding, parking, and interpretive elements that support recreational use while enhancing access to the bRder regional trail network. | Construct high-visibility trailheads and gateway features at major corridor access points. | Arlington Wildlife Area | N/A | N/A | MCDOT | Rio Reimagined leadership; landowners | Number of signature trailheads completed | Long-Term | |
| Trailheads and Amenities | Develop a new trailhead at the Alignment of Johnson Rd and Arlington Canal Rd in Buckeye. The trailhead to provide access to the Ultimate North Bank and River Bed Trail within the Rio Corridor. | Construct high-visibility trailheads and gateway features at major corridor access points. | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Number of signature trailheads completed | Long-Term | |
| Trailheads and Amenities | Develop a new trailhead along the Tuner Rd Alignment along the ultimate north bank in Buckeye. The trailhead to provide access to the North Bank and River Bed Trail within the Rio Corridor. | Construct high-visibility trailheads and gateway features at major corridor access points. | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Number of signature trailheads completed | Long-Term | |
| Trailheads and Amenities | Develop a new trailhead along the Miller Rd Alignment along the ultimate north bank in Buckeye. The trailhead to provide access to the North Bank and River Bed Trail within the Rio Corridor. This Buckeye owned parcel could also include a visitor center. | Construct high-visibility trailheads and gateway features at major corridor access points. | City of Buckeye | 40046010 | N/A | City of Buckeye | Flood Control District of Maricopa County (FCDMC) | Number of signature trailheads completed | Long-Term | |
| Trailheads and Amenities | Develop a new trailhead along the Rainbow Rd Alignment along the ultimate north bank in Buckeye. The trailhead to provide access to the North Bank and River Bed Trail within the Rio Corridor. | Construct high-visibility trailheads and gateway features at major corridor access points. | Bureau of Land Management (BLM) | N/A | Intergovernmental Agreement (IGA) | City of Buckeye | Bureau of Land Management (BLM) | Number of signature trailheads completed | Long-Term | |
| Trailheads and Amenities | Develop a new trailhead along the Jackrabbit Trail Rd Alignment along the south bank in Buckeye. The trailhead to provide access to the South Bank and River Bed Trail within the Rio Corridor. | Construct high-visibility trailheads and gateway features at major corridor access points. | Arizona State Land Department (ASLD) | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Buckeye | Rio Reimagined leadership; landowners | Number of signature trailheads completed | Long-Term | |
| Trailheads and Amenities | Develop a new trailhead at the 43rd Ave Gateway for access to the north bank. | Construct high-visibility trailheads and gateway features at major corridor access points. | City of Phoenix | N/A | N/A | City of Phoenix | Rio Reimagined leadership; landowners | Number of signature trailheads completed | Mid-Term | |
| Trailheads and Amenities | Develop a new trailhead along the Thomas Rd corridor east of Higley Rd. This trailhead would provide future access to the South Canal along the Rio south bank alignment. | Construct high-visibility trailheads and gateway features at major corridor access points. | Arizona State Land Department (ASLD) | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Mesa | Rio Reimagined leadership; landowners | Number of signature trailheads completed | Mid-Term | |
| Trailheads and Amenities | Develop a new trailhead at the Center Street Gateway. This trailhead would provide future access to the South Canal along the Rio south bank alignment. | Construct high-visibility trailheads and gateway features at major corridor access points. | Location To Be Determined | N/A | Acquisition / Easement / Intergovernmental Agreement (IGA) | City of Mesa | Rio Reimagined leadership; landowners | Number of signature trailheads completed | Long-Term | |
| Trailheads and Amenities | Expand river access opportunities. Develop river access locations, overlooks, fishing areas, wildlife viewing facilities, and educational nodes that improve public access to the river system. | Develop designated river access points, overlooks, fishing areas, wildlife viewing facilities, and educational nodes. | Participating jurisdictions | N/A | N/A | Participating jurisdictions; land managers | Environmental agencies; tribal communities; public safety agencies | Number of formal river access locations | Mid-Term | |
| Trailheads and Amenities | Provide comprehensive trailhead amenities. Incorporate parking, restrooms, drinking water, shade structures, bicycle facilities, wayfinding signage, and visitor services at major trailheads. | Provide parking, restrooms, shade, drinking water, bicycle parking, repair stations, wayfinding, and visitor information based on trailhead classification. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Utility providers; sponsors; recreation partners | Percentage of priority trailheads meeting adopted standards | Long-Term | |
| Trailheads and Amenities | Improve universal accessibility. Ensure major trailheads, river access points, pathways, and recreation facilities are designed to provide equitable access for users of all ages and abilities. | Apply universal-design principles to priority pathways, trailheads, overlooks, and river access facilities. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Accessibility advisory groups; community organizations | Number of accessible facilities completed | On-Going | |
| Trailheads and Amenities | Develop destination parks and activity centers. Create destination parks, recreation hubs, gathering spaces, event venues, and family-oriented amenities that attract users throughout the year. | Establish recreation hubs with gathering spaces, nature play, overlooks, event areas, and environmental education facilities. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Schools; nonprofit organizations; cultural partners | Number of destination facilities developed | Mid-Term | |
| Trailheads and Amenities | Integrate educational and cultural amenities. Incorporate cultural resources, public art, outdoor classrooms, interpretive exhibits, and environmental education facilities throughout the corridor. | Install interpretive exhibits, outdoor classrooms, cultural features, public art, and heritage elements at strategic locations. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Tribal communities; educators; historians; artists | Number of interpretive and cultural installations | Mid-Term | |
| Trailheads and Amenities | Improve shade and heat resiliency. Provide shade infrastructure, cooling areas, drinking water stations, and rest areas at strategic locations along pathways and trailheads. | Install shade structures, native shade trees, drinking water, cooling areas, and rest facilities at regular intervals. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Public health agencies; utilities; community organizations | Percentage of priority locations with shade and water | Short-Term | |
| Trailheads and Amenities | Implement unified wayfinding. To improves navigation, reinforces corridor identity, and clearly directs users to pathways, trailheads, access points, parks, destinations, and community amenities. Coordinate signage standards among participating jurisdictions to provide a seamless and recognizable user experience throughout the corridor. | Install consistent directional signs, mileage markers, emergency identifiers, maps, and destination information. | Participating jurisdictions | N/A | N/A | Rio Reimagined leadership | Participating jurisdictions; MAG; emergency responders | Miles of corridor with consistent wayfinding | Short-Term | |
| Trailheads and Amenities | Install bicycle and mobility-support amenities. Provide bicycle and mobility-support amenities at key trailheads, access points, and activity nodes, including secure bicycle parking, repair stations, hydration facilities, seating, shade, and other user-support features. Locate amenities strategically along the corridor to improve comfort, convenience, accessibility, and overall user experience for bicyclists and other pathway users. | Provide bicycle parking, repair stations, charging facilities where appropriate, and connections to mobility hubs. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Transit agencies; bicycle organizations; private sponsors | Number of mobility-support facilities installed | Short-Term | |
| Land Acquisition | Identify strategic land acquisition priorities. Identify and prioritize strategic land acquisitions, easements, and access agreements needed to close pathway gaps, secure trail connections and access points, support future trailheads and amenities, and protect environmentally or culturally significant areas. Coordinate with public agencies, landowners, and other partners to advance acquisition opportunities that support long-term corridor connectivity and implementation. | Prepare a corridor-wide acquisition map identifying properties needed for pathways, trailheads, crossings, habitat protection, and river access. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Rio Reimagined leadership; land management agencies | Priority acquisition map completed | Short-Term | |
| Land Acquisition | Identify strategic land acquisition priorities. Identify and prioritize strategic land acquisitions, easements, and access agreements needed to close pathway gaps, secure trail connections and access points, support future trailheads and amenities, and protect environmentally or culturally significant areas. Coordinate with public agencies, landowners, and other partners to advance acquisition opportunities that support long-term corridor connectivity and implementation. | Prioritize acquisition, easements, and dedications for properties that provide critical regional connections. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Landowners; developers; funding agencies | Number of priority gaps secured | Short-Term | |
| Land Acquisition | Protect riverfront access opportunities. Preserve and secure strategic opportunities for public access to the river corridor through land acquisition, easements, access agreements, and coordination with future development. Prioritize locations that support pathway connections, trailheads, river access points, recreation, and long-term corridor connectivity, while protecting sensitive natural and cultural resources. | Secure public access rights at locations with significant recreation, mobility, ecological, or educational value. | Participating jurisdictions | N/A | N/A | Participating jurisdictions; land managers | Private landowners; tribal communities; nonprofit partners | Acres or access points secured | Short-Term | |
| Land Acquisition | Preserve strategic open space. Identify and protect key open space corridors necessary to maintain future pathway connectivity, habitat preservation, and recreational access. | Acquire or protect lands that support habitat connectivity, flood management, recreation, and scenic character. | Participating jurisdictions | N/A | N/A | Participating jurisdictions; conservation organizations | State and federal agencies; land trusts; landowners | Acres of open space protected | On-Going | |
| Land Acquisition | Utilize conservation easements and alternative acquisition tools. Pursue conservation easements, land dedications, and public-private partnerships where fee-simple acquisition is not feasible. | Pursue easements, land dedications, leases, joint-use agreements, and development incentives where acquisition is not feasible. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Land trusts; developers; private landowners | Acres or corridor miles protected through alternative tools | On-Going | |
| Land Acquisition | Protect sensitive habitat and wildlife corridors. Protect high-value habitat areas, wildlife movement corridors, and environmentally sensitive lands that contribute to long-term ecological health. | Prioritize lands that contain riparian habitat, wetlands, ecological linkages, nesting areas, and wildlife movement corridors. | Participating jurisdictions | N/A | N/A | Resource management agencies | Participating jurisdictions; conservation organizations | Acres of sensitive habitat protected | On-Going | |
| Land Acquisition | Coordinate acquisition with development review. Integrate pathway, trail, and river access acquisition needs into the development review process to secure necessary rights-of-way, easements, and public access as development occurs. Coordinate with property owners, developers, and reviewing agencies to preserve planned connections, close pathway gaps, and advance long-term corridor connectivity. | Require or incentivize pathway easements, river access, open-space frontage, and trail connections through development and redevelopment projects. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Developers; private landowners | Easements and connections secured through development | On-Going | |
| Environmental | Restore native riparian habitat. Expand restoration efforts along the Salt, Gila, and Agua Fria Rivers through native revegetation, wetland enhancement, and habitat rehabilitation projects. | Implement native revegetation, wetland enhancement, and habitat rehabilitation projects along priority river reaches. | Participating jurisdictions | N/A | N/A | Resource management agencies | Participating jurisdictions; tribal communities; conservation organizations | Acres of habitat restored | Short-Term | |
| Environmental | Reduce invasive species impacts. Continue invasive vegetation management and removal programs to improve habitat quality and ecological function. | Establish coordinated invasive plant removal, treatment, revegetation, and monitoring programs. | Participating jurisdictions | N/A | N/A | Land and resource management agencies | Municipalities; tribal communities; volunteer groups | Acres treated and successfully revegetated | On-Going | |
| Environmental | Strengthen wildlife connectivity. Protect and enhance habitat corridors that support wildlife movement and biodiversity throughout the corridor. | Protect and restore habitat linkages between river segments, open spaces, and adjacent natural areas. | Participating jurisdictions | N/A | N/A | Resource management agencies | Participating jurisdictions; landowners; conservation organizations | Habitat corridors protected or restored | On-Going | |
| Environmental | Balance recreation and resource protection. Direct intensive recreation activities to designated locations while protecting environmentally sensitive areas and cultural resources. | Concentrate high-intensity recreation at designated nodes and use boardwalks, overlooks, defined trails, and seasonal controls in sensitive areas. | Participating jurisdictions | N/A | N/A | Land managers | Wildlife agencies; participating jurisdictions; tribal communities | Sensitive areas protected through adopted management measures | On-Going | |
| Environmental | Implement shade and climate-resilience improvements. Implement shade, cooling, and native tree planting programs that improve user comfort while contributing to long-term environmental sustainability. | Expand native tree canopy and incorporate heat-resilient landscape and infrastructure treatments. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Public health agencies; utilities; environmental organizations | Trees planted and shaded pathway mileage | Short-Term | |
| Environmental | Integrate green infrastructure. Utilize bioswales, rain gardens, constructed wetlands, and stormwater management strategies that improve water quality and support habitat restoration | Incorporate bioswales, rain gardens, constructed wetlands, stormwater capture, and low-impact development practices into corridor projects. | Participating jurisdictions | N/A | N/A | Participating jurisdictions; flood control agencies | Utilities; developers; environmental organizations | Number of projects incorporating green infrastructure | Short-Term | |
| Environmental | Improve water quality and groundwater recharge. Implement green infrastructure, stormwater management, and water-harvesting strategies that reduce runoff, improve water quality, and promote groundwater recharge. Integrate these approaches with pathway, trailhead, restoration, and riverfront improvement projects to enhance watershed health and long-term environmental resilience. | Use restoration areas and river-adjacent open spaces to support stormwater treatment, infiltration, and groundwater recharge where feasible. | Participating jurisdictions | N/A | N/A | Water and flood control agencies | Participating jurisdictions; utilities; resource agencies | Water-quality and recharge projects implemented | Mid-Term | |
| Environmental | Expand environmental education. Promote environmental awareness through educational programming, interpretive opportunities, citizen science initiatives, and community stewardship activities. | Develop environmental interpretation, outdoor classrooms, school partnerships, citizen science, and guided programs. | Participating jurisdictions | N/A | N/A | Participating jurisdictions; education partners | Schools; tribal communities; nonprofit organizations | Programs offered and annual participation | Short-Term | |
| Environmental | Protect and interpret cultural resources. Protect, interpret, and celebrate the cultural, Indigenous, agricultural, and historical heritage of the river corridor through planning, design, and public engagement. | Coordinate with tribal communities and cultural-resource specialists to protect and interpret significant sites and corridor histories. | Participating jurisdictions | N/A | N/A | Participating jurisdictions; tribal communities | Historic preservation and cultural organizations | Cultural resources protected and interpreted | On-Going | |
| Environmental | Establish ecological monitoring and adaptive management. Monitor ecological conditions and restoration performance to guide management actions, prioritize improvements, and support long-term ecosystem health and resilience. | Monitor habitat, vegetation, water quality, and wildlife conditions and adjust management practices based on documented outcomes. | Participating jurisdictions | N/A | N/A | Resource management agencies | Universities; tribal communities; participating jurisdictions | Monitoring reports completed and management actions updated | On-Going | |
| Operations & Maintenance | Establish corridor-wide maintenance standards. Develop consistent maintenance standards and operational procedures for pathways, trailheads, restoration areas, and public facilities throughout the corridor. | Adopt consistent standards for pathways, trailheads, landscaping, natural areas, signs, furnishings, and public facilities. | Participating jurisdictions | N/A | N/A | Rio Reimagined leadership | Participating jurisdictions; managing agencies | Regional maintenance standards adopted | Short-Term | |
| Operations & Maintenance | Define long-term maintenance responsibilities. Establish clear maintenance and operational responsibilities among participating jurisdictions, agencies, and partners. | Execute agreements identifying ownership, inspection, repair, landscaping, habitat management, and operational responsibilities. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Flood control agencies; land managers; tribal communities | Maintenance agreements executed | Short-Term | |
| Operations & Maintenance | Secure sustainable operations funding. Identify dedicated funding sources to support long-term maintenance, rehabilitation, and asset management needs. | Establish dedicated and recurring funding sources for maintenance, rehabilitation, staffing, and replacement needs. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Rio Reimagined leadership; funding partners; sponsors | Annual operations funding secured | On-Going | |
| Operations & Maintenance | Implement an asset management system. Utilize data-driven asset management programs to monitor infrastructure condition, prioritize maintenance needs, and guide investment decisions. | Maintain an inventory of pathways, trailheads, signs, structures, amenities, and natural-resource assets. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Rio Reimagined leadership; managing agencies | Assets inventoried and inspection schedules established | Short-Term | |
| Operations & Maintenance | Enhance corridor safety and emergency response. Implement corridor-wide safety measures including emergency access, mile markers, lighting where appropriate, visibility improvements, and provide emergency access. | Develop emergency-response protocols and install mile markers, location identifiers, warning signs, and emergency-access features. | Participating jurisdictions | N/A | N/A | Participating jurisdictions; public safety agencies | Land managers; emergency service providers | Emergency plan adopted and markers installed | On-Going | |
| Operations & Maintenance | Apply CPTED and appropriate security measures. Incorporate CPTED principles and context-sensitive security measures to improve safety, visibility, and security while maintaining an inviting public environment. | Improve sightlines, vegetation management, access control, and lighting at appropriate urban locations without adversely affecting habitat. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Public safety agencies; environmental partners | Priority safety improvements completed | Short-Term | |
| Operations & Maintenance | Establish a regional stewardship program. Establish volunteer and stewardship programs that support corridor maintenance, habitat restoration, monitoring, and community engagement. | Coordinate volunteer cleanups, restoration events, trail maintenance, citizen science, and community stewardship activities. | Participating jurisdictions | N/A | N/A | Rio Reimagined leadership | Nonprofit organizations; businesses; schools; community groups | Annual volunteer participation and service hours | Short-Term | |
| Operations & Maintenance | Deploy smart corridor technologies. Incorporate visitor monitoring, environmental sensors, digital wayfinding, trail counters, and real-time information systems to improve corridor operations and decision making. | Install trail counters, environmental sensors, real-time condition information, and digital visitor-information systems. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | MAG; universities; technology partners | Monitoring systems installed and reporting data | Mid-Term | |
| Operations & Maintenance | Coordinate year-round programming. Support recreation programs, educational activities, community events, and volunteer initiatives that encourage year-round use and stewardship of the corridor. | Support recreation, cultural, educational, and stewardship activities that encourage corridor use and community ownership. | Participating jurisdictions | N/A | N/A | Participating jurisdictions | Tribal communities; nonprofit organizations; schools; recreation providers | Number of annual programs and participants | On-Going | |
| Operations & Maintenance | Report implementation progress. Track and communicate progress on plan recommendations, projects, funding, and key milestones to support accountability and on-going implementation. | Publish periodic updates documenting completed projects, expenditures, maintenance conditions, environmental outcomes, and system use. | Participating jurisdictions | N/A | N/A | Rio Reimagined leadership | Participating jurisdictions; project partners | Implementation reports published | On-Going |
Active Transportation Network Prioritization
This content is currently available on desktop devices only. Please use a desktop or larger-screen device to access it.
Corridor Segment Prioritization
| No. | Segment Location | Area | Jurisdiction | Agency | Proposed Project Description | Miles | Property Owners | Acquisition / Easement Required | Relative Order of Magnitude | Priority |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | MC-85 - Ult North Bank to W. Southern Ave | Buckeye | Maricopa County | MCDOT | Multi-Use Pathway - 12 ft Wide on East Side | 3.14 | Maricopa County ROW | No | $3,922,348 | Mid-Term |
| 2 | Rooks Rd - Ult. Gila River North Bank to Lower River Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway - 12 ft Wide on East Side | 0.91 | City of Buckeye ROW | No | $1,137,547 | Long-Term |
| 3 | Rooks Rd - W. MC-85 to Maricopa Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway - 12 ft Wide on East Side | 1.01 | City of Buckeye ROW / BWCDD / UPRR | Yes | $1,258,759 | Mid-Term |
| 4 | Rainbow Rd - Ult. North Bank to Buckeye Canal Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway - 12 ft Wide on West Side | 1.81 | City of Buckeye / BWCDD | No | $2,265,152 | Long-Term |
| 5 | Rainbow Rd - Buckeye Canal Rd to Broadway Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway - 12 ft Wide on West Side | 1.44 | City of Buckeye ROW / BWCDD / UPRR | Yes | $1,794,271 | Mid-Term |
| 5 | Jackrabbit Rd - W, Lower River Rd to Buckeye Canal Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway - 12 ft Wide on West Side | 1.77 | City of Buckeye / BWCDD | No | $2,214,252 | Long-Term |
| 6 | Jackrabbit Rd - Buckeye Canal Rd to W. Lower Buckeye Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway - 12 ft Wide on West Side | 2.3 | City of Buckeye / BWCDD | Yes | $2,870,028 | Mid-Term |
| 7 | W. Lower Buckeye Rd - Jackrabbit Rd to Perryville Rd | Buckeye | City of Buckeye | Buckeye | Multi-Use Pathway - 12 ft Wide on South Side | 1 | City of Buckeye ROW | No | $1,245,739 | Mid-Term |
| 1A | S. Estrella Parkway - Buckeye Canal to Bullard Ave | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway - 12 ft Wide on West Side | 1.03 | City of Goodyear ROW / UPRR / BWCDD | Yes | $1,293,561 | Short-Term |
| 1B | S. Estrella Parkway - Buckeye Canal to Bullard Ave | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway - 12 ft Wide on East Side | 1.31 | City of Goodyear ROW / UPRR / BWCDD | Yes | $1,634,706 | Short-Term |
| 2A-1 | S. Estrella Parkway - UPRR - W. Goodyear Blvd South | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway - Add on 4 ft to Existing Sidewalk on West Side for 12 ft wide MUP | 1.45 | City of Goodyear ROW | No | $1,814,631 | Short-Term |
| 2B-1 | S. Estrella Parkway - W. Lower Buckeye Pkwy - W. Goodyear Blvd South | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway - Add on 4 ft to Existing Sidewalk on East Side for 12 ft wide MUP | 1.15 | City of Goodyear ROW | No | $1,440,578 | Short-Term |
| 2A-2 | S. Estrella Parkway - Goodyear Blvd South to Goodyear Blvd North | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway - 12 ft wide on West Side | 0.55 | City of Goodyear ROW | No | $689,631 | Short-Term |
| 2B-2 | S. Estrella Parkway - Goodyear Blvd South to Goodyear Blvd North | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway - 12 ft wide on East Side | 0.55 | City of Goodyear ROW | No | $689,631 | Short-Term |
| 3 | S. Sarival Ave - Dunlap Rd to W. Yuma Rd | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway - 12 Ft Wide on West Side | 1.49 | City of Goodyear ROW | No | $1,857,008 | Mid-Term |
| 4A | S. Cotton Ln - W. Estrella Pkwy to MC-85 | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway - 12 Ft Wide on West Side | 3.24 | City of Goodyear ROW | No | $4,046,165 | Long-Term |
| 4B | S. Cotton Ln - W. Estrella Pkwy to MC-85 | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway - 12 Ft Wide on East Side | 3.25 | City of Goodyear ROW | No | $4,058,239 | Long-Term |
| 5 | W. Lower Buckeye Rd - S. Cotton Ln to Citrus Rd | Goodyear | City of Goodyear | Goodyear | Multi-Use Pathway - 12 Ft Wide on South Side | 0.5 | City of Goodyear ROW | No | $619,555 | Long-Term |
| 1 | S. Avondale Rd - El Mirage Rd to W. Lower Buckeye Rd | Avondale | City of Avondale | Avondale | Multi-Use Pathway - 12 Ft Wide on East Side | 2.26 | City of Avondale ROW | No | $2,827,652 | Mid-Term |
| S. Avondale Rd - Bridge | Avondale | City of Avondale | Avondale | Add Standard 6 ft Wide Bicycle Lanes on Bridge - No Middle Lane | ||||||
| 2A | S. El Mirage Rd - Indian Springs Road to Broadway Rd | Avondale | City of Avondale | Avondale | Multi-Use Pathway - 12 Ft Wide on East Side | 1.74 | City of Avondale ROW | No | $2,174,479 | Long-Term |
| 2B | S. El Mirage Rd - Broadway Rd to Durango St | Avondale | City of Avondale | Avondale | Multi-Use Pathway - Add on 2 Ft to 6 Ft to Existing Concrete Pathway for 12 Ft Wide on East Side | 1.43 | City of Avondale ROW | No | $1,787,405 | Long-Term |
| 2C | S.El Mirage Rd - Lower Buckeye Rd to Durango St. | Avondale | City of Avondale | Avondale | Multi-Use Pathway - 12 Ft Wide on East Side | 0.11 | City of Avondale ROW | No | $142,045 | Long-Term |
| 3A | S. Dysart Rd - Buckeye Canal Rd to W. Lower Buckeye Rd | Avondale | City of Avondale | Avondale | Multi-Use Pathway - 12 Ft Wide on East Side | 0.74 | City of Avondale ROW | No | $927,320 | Long-Term |
| 3B | S. Dysart Rd - Ult. North Bank to Buckeye Canal Rd | Avondale | City of Avondale | Avondale | Multi-Use Pathway - 12 Ft Wide on East Side | 1.96 | City of Avondale ROW | No | $2,449,811 | Long-Term |
| 4A | S. Litchfield Rd - W. Broadway Rd. to Lower Buckeye Rd | Avondale | City of Avondale | Avondale | Multi-Use Pathway - 12 Ft Wide on East Side | 0.98 | City of Avondale ROW | No | $1,222,301 | Long-Term |
| 4B | S. Litchfield Rd (Alignment) - Ult. North Bank (Southern Ave Alginment) to Lower Buckeye Rd | Avondale | City of Avondale | Avondale | Multi-Use Pathway - 12 Ft Wide on East Side | 2 | City of Avondale ROW | Yes | $2,497,159 | Long-Term |
| 5A | W. Lower Buckeye Rd - Litchfield Rd to Dysart Rd | Avondale | City of Avondale | Avondale | Multi-Use Pathway - 12 ft Wide on South Side | 1.54 | City of Avondale ROW | No | $1,929,214 | Long-Term |
| 5B | W. Lower Buckeye Rd - El Mirage Rd to 107th Ave | Avondale | City of Avondale | Avondale | Multi-Use Pathway - 12 ft Wide on South Side | 1.71 | City of Avondale ROW | No | $2,137,784 | Long-Term |
| 1 | S. 91st Ave - W. Baseline Rd to W. Broadway Rd | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway - 12 Ft Wide on West Side | 2.27 | City of Phoenix ROW | No | $2,834,991 | Long-Term |
| S. 91st Ave - W. Lower Buckeye Rd to W. Pima Rd | Phoenix | City of Phoenix | Phoenix | Buffered Bicyele Lane - Paint Striping with Traffic Post | 0.3 | City of Phoenix ROW | No | $95,040 | ||
| 2 | S. 67th Ave - W. Southern Ave to Buckeye Rd | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway - 12 Ft Wide on East Side | 1.4 | City of Phoenix ROW | No | $1,754,261 | Long-Term |
| 3A | S. 51st Ave - W. Olnly Ave to W. South Mountain Ave | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway - 12 Ft Wide on West Side | 0.43 | City of Phoenix ROW | No | $540,956 | Long-Term |
| 3B | S. 51st Ave - South of W. Baseline Rd to South of W. Maldonado Rd | Phoenix | City of Phoenix | Phoenix | Buffered Bicyele Lane - Paint Striping with Traffic Post with Roadway Expansion | 0.97 | City of Phoenix ROW | No | $308,400 | Long-Term |
| 3C | S. 51st Ave - W. Broadway Rd Bridge | Phoenix | City of Phoenix | Phoenix | Buffered Bicycle Lane - Paint Striping with Traffic Post | 1.14 | City of Phoenix ROW | No | $361,440 | Long-Term |
| 4A | S. 35th Ave - W. Dobbins Rd to Cesar Chavez Park Dr | Phoenix | City of Phoenix | Phoenix | Buffered Bicycle Lane - Paint Striping with Traffic Post | 1.31 | City of Phoenix ROW | No | $415,560 | Long-Term |
| 4B | S. 35th Ave - Cesar Chavez Park Dr to W. Buckeye Rd | Phoenix | City of Phoenix | Phoenix | Reduce Lanes from 12 Ft width to 10.5 Ft width to add Buffered Bicycle Lane with Traffic Post | 8.9 | City of Phoenix ROW | No | $2,818,080 | Long-Term |
| 4C | S. 35TH Ave - W. Buckeye Rd to Roosevelt St | Phoenix | City of Phoenix | Phoenix | Remove Northbound Lane and Add Buffered Bicycle Lane - Paint Striping with Traffic Post | 3 | City of Phoenix ROW | No | $949,560 | Long-Term |
| 5A | S. 19th Ave - W. Southern Ave to MLK JR Blvd | Phoenix | City of Phoenix | Phoenix | Remove Southbound Lane and Add Buffered Bicycle Lane - Paint Striping with Traffic Post | 1.96 | City of Phoenix ROW | No | $2,455,492 | Long-Term |
| 5B | S. 19th Ave - MLK JR. Blvd to I-10 | Phoenix | City of Phoenix | Phoenix | Multi-Use Pathway - Add on 4 ft to Existing Sidewalk on East Side for 12 ft wide MUP | 3.81 | City of Phoenix ROW | No | $1,588,463 | Long-Term |
| 6 | S. 7th Ave - Mohave St to McDowell Rd | Phoenix | City of Phoenix | Phoenix | Buffered Bicycle Lane - Paint Striping with Traffic Post | 4.77 | City of Phoenix ROW | No | $1,511,160 | Long-Term |
| 7A | S. 7th St - North of E. Victory St to E. University Dr (Bridge) | Phoenix | City of Phoenix | Phoenix | Buffered Bicycle Lane - Paint Striping with Traffic Post | 0.54 | City of Phoenix ROW | No | $171,480 | Long-Term |
| 7B | S. 7th St - North of E. Watkins St to E. Apache St | Phoenix | City of Phoenix | Phoenix | Buffered Bicycle Lane - Paint Striping with Traffic Post | 2.61 | City of Phoenix ROW | No | $828,000 | Long-Term |
| 8A | S. 16th St - E. Baseline Rd to I-17 | Phoenix | City of Phoenix | Phoenix | Remove Southbound Land and Add Buffered Bicycle Lane - Paint Striping with Traffic Post | 6.58 | City of Phoenix ROW | No | $2,083,200 | Long-Term |
| 8B | S. 16th St - I-17 to Washington | Phoenix | City of Phoenix | Phoenix | Buffered Bicycle Lane - Paint Striping with Traffic Post | 2.88 | City of Phoenix ROW | No | $912,000 | Long-Term |
| 8C | S. 16th St. - E. Roosevelt St to E. McDowell Rd | Phoenix | City of Phoenix | Phoenix | Buffered Bicycle Lane - Paint Striping with Traffic Post | 0.84 | City of Phoenix ROW | No | $267,240 | Long-Term |
| 9 | S. 24th St - E. Baseline Rd to Magnolla St | Phoenix | City of Phoenix | Phoenix | Buffered Bicycle Lane - Paint Striping with Traffic Post | 6.17 | City of Phoenix ROW | No | $1,953,480 | Long-Term |
| 1 | N. Priest Rd - Rio Salado Pkwy to W. Washington St | Tempe | City of Tempe | Tempe | Multi-Use Pathway - 12 ft Wide on West Side & East Side | 0.33 | City of Tempe ROW | No | $412,500 | Mid-Term |
| 2 | N. Mill Ave - Gammage Pkwy to E. Curry Rd | Tempe | City of Tempe | Tempe | Reduce Lane Width for Bike Lane | 1.89 | City of Tempe ROW | No | $598,320 | Long-Term |
| 3 | N. Rural Rd - US-60 to E. Curry Rd | Tempe | City of Tempe | Tempe | Buffered Bicycle Lane - with Curb | 7.48 | City of Tempe ROW | No | $2,370,600 | Long-Term |
| 4 | E. Curry Rd - N. Scottsdale Rd to McClintock Dr | Tempe | City of Tempe | Tempe | Buffered Bicycle Lane - Paint Striping with Traffic Post | 1.93 | City of Tempe ROW | No | $612,600 | Long-Term |
| 5 | S. McClintock Dr - Apache Blvd to Loop 202 (North Side) | Tempe | City of Tempe | Tempe | Multi-Use Pathway - 12 Ft Wide on West Side | 0.75 | City of Tempe ROW | No | $937,500 | Mid-Term |
| 1 | S. Dobson Rd - W. Southern Ave to N. Mesa Riverview Dr | Mesa | City of Mesa | Mesa | Future Complete Street with Tempe Trolly Connection - 2029 MAG CIP | City of Mesa ROW | No | Mid-Term | ||
| 2 | N. Center St - E. McKellips Rd to W. Lehi Rd | Mesa | City of Mesa | Mesa | Remove Southbound Land and Add Buffered Bicycle Lane - with Protected Curb | 0.6 | City of Mesa ROW | No | $158,400 | Mid-Term |
| 3 | N. Val Vista - E. Brown Rd to Loop 202 (North) | Mesa | City of Mesa | Mesa | Multi-Use Pathway - 12 Ft Wide on West Side | 0.5 | City of Mesa ROW | No | $625,000 | Mid-Term |
| 4 | N. Power Rd - E. McDowell Rd to N. Bush Hwy | Mesa | City of Mesa | Mesa | City of Mesa Just Constructed 12 ft wide Asphalt Multi-Use Pathway on East Side | City of Mesa ROW | No | COMPLETED | Short-Term | |
| 5 | N. Bush Hwy - Power Rd to Saguaro Lake | Mesa | Maricopa County | MCDOT | Multi-Use Pathway - 12 Ft Wide on East Side | 8.35 | Maricopa County ROW | No | $10,432,528 | Long-Term |
| 6 | E. Thomas Rd - Power Rd to N. Recker Rd | Mesa | City of Mesa | Mesa | Buffered Bicycle Lane - with Curb | 4.12 | City of Mesa ROW | No | $1,304,160 | Short-Term |
| 7 | Salt River Sand & Rock Road - Higley Rd to South Canal | Mesa | Multi-Use Pathway - 12 Ft Wide on East Side | 0.5 | Private | Yes | $630,445 | Short-Term |